ATPMM – a Guide to TELSOM/ATRC Project Approval Process Workshop on ASEAN TELSOM Project Implementation & Fundi PowerPoint Presentation
Download Presentation
ATPMM – a Guide to TELSOM/ATRC Project Approval Process Workshop on ASEAN TELSOM Project Implementation & Fundi

Loading in 2 Seconds...

play fullscreen
1 / 20

ATPMM – a Guide to TELSOM/ATRC Project Approval Process Workshop on ASEAN TELSOM Project Implementation & Fundi - PowerPoint PPT Presentation


  • 150 Views
  • Uploaded on

ATPMM – a Guide to TELSOM/ATRC Project Approval Process Workshop on ASEAN TELSOM Project Implementation & Funding Management Manual (ATPMM ) Phnom Penh, 30 May 2014. Outlines. Project approval processes Approval of AICTF-funded projects Approval stages

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'ATPMM – a Guide to TELSOM/ATRC Project Approval Process Workshop on ASEAN TELSOM Project Implementation & Fundi' - hans


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

ATPMM – a Guide to

TELSOM/ATRC Project Approval Process

Workshop on ASEAN TELSOM Project Implementation &

Funding Management Manual (ATPMM)

Phnom Penh, 30 May 2014

outlines
Outlines
  • Project approval processes
  • Approval of AICTF-funded projects
  • Approval stages
  • Annual budget under ASEAN ICT Fund
  • Approval of projects supported by DP’s ASEAN cooperation fund
project approval processes
Project Approval Processes
  • TELSOM/ATRC cooperation projects require the approval of sectoral bodies (TELSOM/ATRC) at the bodies’ regular meetings or, in some cases, on an ad-referendum basis.
  • Two main approval processes:
    • Approval process for projects to be funded using the ASEAN ICT Fund (AICTF) or Japan-ASEAN ICT Fund
    • Approval process for projects to be funded using Dialogue Partner’s ASEAN Cooperation Funds
approval of aictf funded projects step 1 21
Approval of AICTF-fundedProjects (step 1, 2)
  • Step 1 and 2
    • Project proponent puts forward the project concept to the relevant TELSOM/ATRC WG for consideration, assessment, and approval by consensus.
    • Project concept shall be assessed and ranked by the relevant WG using the TELSOM Assessment Criteria (PG 6, 7 and 8)
approval of aictf funded projects step 3 41
Approval of AICTF-fundedProjects (step 3, 4)
  • Step 3
    • Project proponent puts forward the detailed project proposal document in ASEAN Full Project Document (PG 2), ), which also includes a proposed budget, to TELSOM for endorsement.
    • TELSOM examines and ranks all project proposals across WGs with a view to achieve the milestones and goals set by the Ministers or ASEAN Leaders.
  • Step 4
    • The final approval on the project shall be decided by TELMIN at its annual Ministerial Meeting.
approval of aictf funded projects step 51
Approval of AICTF-fundedProjects (step 5)
  • Step 5
    • Once the funding has been approved by TELMIN for AICTF support or by the Dialogue Partner who provides the funding support, the project proponent implements the project.
approval stages 3 3
Approval Stages (3/3)
  • Note: The timing of the planning stages is subject to the scheduling of the Ministerial, Senior Officials and JWG/WG meetings
annual budget under aictf
Annual Budget under AICTF
  • TELSOM and ATRC shall recommend an annual budget for projects to be implemented in the next Work Cycle to TELMIN for approval.
  • The allocation of the TELMIN approved budget shall be proposed by the respective JWGs to TELSOM or ATRC for approval, based on the approved project proposals.
approval of projects supported by dp s asean cooperation fund step 1 21
Approval of Projects Supported by DP’s ASEAN Cooperation Fund (step 1, 2)
  • Project proponent puts forward the project proposal in the Full Project Document format (PG 2) to ASEAN Secretariat for a preliminary assessment.
  • The project proposal undergoes a pre-appraisal to evaluate its completeness through a pre-appraisal meeting (PAM) of a pre-appraisal team within ASEAN Secretariat.
approval of projects supported by dp s asean cooperation fund step 3 41
Approval of Projects Supported by DP’s ASEAN Cooperation Fund (step 3, 4)
  • Step 3
    • The project proposal undergoes a review by a Project Appraisal Committee (PAC) within ASEAN Secretariat.
  • Step 4
    • Once the project proposal has received a PAC endorsement, it shall be sent to TELSOM for consideration and approval.
approval of projects supported by dp s asean cooperation fund step 5 6 71
Approval of Projects Supported by DP’s ASEAN Cooperation Fund (step 5,6,7)
  • Step 5
    • Once the proposal is endorsed by TELSOM, ASEAN Secretariat tables the proposal for consideration of the ASEAN Committee of Permanent Representative (CPR) including the request for funding source(s).
  • Step 6
    • Based on CPR’s comments, the Project Proponent may revise the project proposal to meet certain requirements.
    • Once CPR has approved the proposal, it will be forwarded to DP through the relevant channel for funding support.