Oconto Falls School District Phase II Discussion

Loading in 2 Seconds...

play fullscreen
1 / 27

Oconto Falls School District Phase II Discussion - PowerPoint PPT Presentation


  • 145 Views
  • Uploaded on

Oconto Falls School District Phase II Discussion. November 11, 2013. Presentation. Introduction Successful Completion Phase I Phase II – Facilities Preservation Options Moving Forward Project Financing Next Steps. Phase I Energy Savings . 3. Phase I and Phase II Funding.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Oconto Falls School District Phase II Discussion' - graham


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Oconto Falls

School District

Phase II Discussion

November 11, 2013

slide2

Presentation

  • Introduction
  • Successful Completion Phase I
  • Phase II – Facilities Preservation
  • Options Moving Forward
  • Project Financing
  • Next Steps
phase i and phase ii funding
Phase I and Phase II Funding

Phase I - Performance Contract

  • Self Funded – Heavily Weighted on Energy Savings
  • Capital Equipment Lease financed at 2.49% over 10 years

Phase II -Performance Contract

  • Use of Act 32 Revenue Limit Exemption heavily weighted on Future Cost Avoidance with some Energy Cost Savings
  • Or the District’s Financial Consultant will identify creative financing options – Using ongoing low finance rates
  • Existing Contract can be Modified for ease and limit cost

4

phase i funding source
Phase I Funding Source

Energy Savings Project

Energy Savings

Operations & Maintenance Savings

Long Term Capital Avoidance Savings

Funds for Facility

Improvements

phase ii potential funding sources
Phase II Potential Funding Sources

Preservation of Facilities

Energy Savings

Operations & Maintenance Savings

Long Term Capital Avoidance Savings

Funds for Facility

Up Keep

slide8

OFES Window Replacement Phase II

Original interior wood fame windows are Inefficient and a pose a security concern

New High Efficiency Windows – Full Aluminum

facility improvements measures needs
Facility Improvements Measures & Needs

Tuck Pointing

  • Parking Lot Restoration/Seal
  • Coat Work

Washington Middle School

High School

slide10

Facility Improvements Measures & Needs

Window Film

Low-E

Parking lot Upkeep

slide11

IT Space Cooling

Needs

District office boiler

slide12

Facilities Security Enhancements

  • Interior Shatter
  • Resistance Film

Expansion of Current Security Camera Systems

facility improvements measures needs1
Facility Improvements Measures & Needs

Tuck Pointing

OFHS

Shingled

Roofing

Section

VoIP System

Voice Over internet Protocol

Upgrade/expand existing VoIP to reduce phone service cost and system maintenance cost

slide17

Roofing Replacement Recently Completed

Roofing Work Completed in 2012

slide18

OFHS Roofing

Inspection Completed

Spring 2012

1–2 Year Timeframe

2–5 Year Timeframe

5+ Year Timeframe

slide19

OFHS Roofing

OFHS: Reroof

Priority 1 sections with older Priority 2 sections which have asphalt shingles

High School Roofing Overview

slide20

OFHS Roofing

Replace

Priority 2 ballasted

rubber roof

Leaking Areas

OFES Roofing Overview

slide21

WMS Roofing

Inspection Completed

Spring 2012

1–2 Year Timeframe

2–5 Year Timeframe

5+ Year Timeframe

slide22

WMS Roofing

WMS: Reroofing of Priority 1 and surrounding asphalt shingled Priority 2 sections

Middle School Roofing Overview

slide23

Abrams Roofing

Inspection Completed

Spring 2012

1–2 Year Timeframe

2–5 Year Timeframe

5+ Year Timeframe

slide24

Abrams Roofing

Reroofing of Priority 1 and surrounding asphalt shingled Priority 2 old section only

Abrams Elementary Roofing Overview

slide25

2011 Wisconsin Act 32 – Revenue Limit Exemption

Wisconsin Act 28 was amended in 2011 by Act 32…. a District may adopt a resolution to increase revenue limit equal to amount spent on a project for energy efficiency measures ….. using bonds or notes issued to finance the project if:  

  • The project results in the avoidance of, or reduction in, energy or operational costs;
  • The project is governed by a performance contract entered into under Municipal Law Sec.66.0133; and (only a WI certified ESCO can be used)
  • The bonds or notes issued to finance the project for periods not exceeding 20 years.

Oconto Falls School District can pass a resolution up to the $1M for ESPC projects with a School Board resolution. If the Energy Efficiency Project exceeds the $1M Cap, the Board can still pass a resolution which will track through the following:

  • A 30 day hold will be placed on the Levy to allow for a voter petition. If within the 30 days, a Voter petition is successful, the Levy must be approved by a Voter Referendum
  • If there is no successful Voter petition within the 30 days, the Board passes a resolution for the Revenue Limit Override to allow bond sale and Levy implementation
next step
Next Step

School Board Resolution

  • Approval for Signature on Ameresco Project Development Agreement
  • Schedule Next Meetings to discuss District Goals and Proceed
  • Detailed Audit and Comprehensive Report, showing:
    • Improvement Measures and Firm Costs
    • Guaranteed Savings and Funding Options for Improvements
  • Exit Fee - $9,900 (Paid Only in the Event the District chooses not to Implement the Project)for engineering and other expenses incurred
  • Detailed Energy Audit costs will be rolled into the project financing.
  • There are no up-front costs to proceed at this time.
ameresco information and resources
AMERESCO Information and Resources
  • Please visit our website:
  • www.ameresco.com
    • Services
    • Press Releases
    • Case Studies
    • Videos

Kent Wolf

Business Development Manager

612.315.6940

Cell: 612.804.6274

Ameresco-Midwest Region

kwolf@ameresco.com

To see the latest Ameresco news and events – add a Google “Alert” for Ameresco

Thank You