1 / 13

Oconto Falls School District

Energy Performance Progress Report. Oconto Falls School District. November 2012 Update. Ameresco Update . Introduction.

cortez
Download Presentation

Oconto Falls School District

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Energy Performance Progress Report Oconto Falls School District November 2012 Update

  2. Ameresco Update Introduction This presentation is designed to provide the Oconto Falls School District with a brief update of the project status and the improvements being implemented. Ameresco will be providing these monthly updates until the project is completed.

  3. Timeline

  4. Project Summary and Status

  5. Ameresco Update • Recent Activities • District Notice to Proceed – Received in October • Final subcontractor qualification sent and received • Subcontractor bid review, selection, and agreement • IT Solutions: working with District IT Manager for hardware selection

  6. Ameresco Update When Does Energy Savings Benefit Begin? Energy Savings Benefit: Immediate - Partial savings begins as retrofit work progresses At Completion – Savings generated when system is installed and fully integrated

  7. Ameresco Update - Continued

  8. Ameresco Update - Continued

  9. Ameresco Update Bell / PA System Replacement STATUS: Abrams Elementary - Complete Oconto Falls Emanatory School - Not Yet Started Both Schools were in need of a new Public Address/Bell Notification System upgrade. The Abrams system completely failed as a result of a lighting strike this summer. The Abrams installed system head end(hardware and software) was completed and operational on September 11th. Photo taken during installation Benefits/Results • School wide notification of activities and events • Capital Budget Savings

  10. Ameresco Update Roof Replacement – HS Old Gym STATUS: Pre-Bid Walk through Complete Roofing section is leaking and in need of a complete replacement. A new 30 year Roof has been designed with construction anticipated for Nov 12th. Benefits/Results • Elimination of the potential for roof leakage • causing interior water damage • Capital Budget Savings • Operational and Maintenance Savings

  11. Ameresco Update Lighting Retrofits and Controls STATUS: LED Pilot Light Study In Progress Ameresco installed two different manufacturer’s LED lighting systems in August down two separate halls at OFES. Each hall has three fixtures (same type) installed for testing purposes. The information and analysis from this pilot program will be the basis for interior LED lighting upgrades. • Benefits/Results • Energy Savings • Operational and Maintenance Savings

  12. Next Steps • Roofing work to commence • Construction Kickoff meeting(December) – Key staff members • Material selection and procurement • Review de-scoping changes Technical

  13. AMERESCO Information and Resources • Please visit our website: • www.ameresco.com • Services • Press Releases • Case Studies Kent Wolf Business Development Manager 952.942.5142 ext. 4690 Cell: 612.804.6274 Ameresco-Midwest Region 9855 West 78th Street, Suite 310 Eden Prairie, MN 55344 kwolf@ameresco.com Thank You

More Related