CE Marking For ALMA Prototype Antenna 2006/06/22 – AAS-F Toulouse. CE Marking. Schedule for actions : May 2006 : status of the actions conducted up to end of 2005. June 2006 : teleconferences with EIE to update the answers to BV reservations. July 2006 : actions with BV

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

CE Marking For ALMA Prototype Antenna 2006/06/22 – AAS-F Toulouse


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1
CE Marking
  • For ALMA Prototype Antenna
  • 2006/06/22 – AAS-F Toulouse
slide2

CE Marking

  • Schedule for actions :
    • May 2006 : status of the actions conducted up to end of 2005.
    • June 2006 : teleconferences with EIE to update the answers to BV reservations.
    • July 2006 : actions with BV
      • meetings BV/EIE/AAS-F review of updated answers, collection of proofs and preparation of the files.
      • Transmission of the whole CE marking dossier to BV
      • Feed-back from BV on the CE marking dossier
    • September 2006 : actions with BV
      • Transmission of updated CE marking dossier to BV
      • Final Feed-back from BV on CE marking dossier
  • Following these actions, AAS-F Quality Director will issue a CE marking declaration with reservations. It is AEM objective that all the remaining open reservations are the consequence of ESO constraints or requirements.
slide3
Spare parts
  • For ALMA Prototype Antenna
  • 2006/06/22 – AAS-F Toulouse
slide4

Spare Parts

  • According the agreement between ESO and AEC ( => cfr ESO lettre / ref 8114/LET/CP/RFI-gmv dated Dec 17th, 2004) , AEC must deliver to ESO Spare elements listed into the AEC documentation ref ALMA-EUR-LIS-AEC-58969-0010.
    • Spare Kits will be deliverable at VLA site at Soccorro in the shortest possible time
      • Particular attention drawn to:
        • AZ/EL Drive segment : AEC proposes to complete the on-going analysis ( wrt to failure recorded in EL drive) to define the recovery action and to complete the global procurement of spare parts.
        • Encoder : delivery of the item is foreseen early in September 2006 at VLA ( due to long lead manufacturing process )