An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Local level integration SIA and EIA ETC Energy Lyon, 20 July 2005

  2. What has been done? • Local parties subcontracted: framework and guidance established by ETC • Environmental Impact Assessment: • PECC2 (government owned consultancy company) • Social Impact Assessment: • RCEE (ngo / private consultancy company) • Draft reports are available

  3. EIA • No major environmental issues • The environmental costs: • Low costs • Reforestation, recovery and protection of forest areas, • The costs to keep the areas along inter-commune road system during construction period clean

  4. SIA Ha Dung2 • no electricity, expected from HPP Krong Pa II • (free) kerosene and (free) fuel wood for lighting • Diesel engine for rice milling • Slash and burn agriculture • Very few productive activities Kon Lanh1 • grid connected since February 2004 • Free access • TV in “Rong House” • Rice cookers • Lighting at outside toilet • Permanent living • Very few productive activities

  5. SIA Comparative research in 2 villages Expected impacts: • Consumptive use: lighting and tv (40% watch frequently) • Social conditions: schools and cultural house • Productive uses: few impacts, no investment capacity Households can afford neither connection nor fee Recommendations: • Stimulate productive activities (e.g. project for repair and maintenance workshop) • Financial support needed (both for access and for development of productive activities)

  6. Load forecast • Ha Dung • 20 Mwh, 10 kW • 47 Mwh (after 5 years) • All 9 villages: 95 kW

  7. What’s next? • Peer review: • SIA: ETC, GLPC, IED? • EIA: ETC, GLPC, IoE? • How to make sure that something will happen with the results? • Local presentation? • Funds for implementation?