Lessons Learned in Integrating Risk Management and Process Validation

Loading in 2 Seconds...

play fullscreen
1 / 39

Lessons Learned in Integrating Risk Management and Process Validation - PowerPoint PPT Presentation


  • 401 Views
  • Uploaded on

Lessons Learned in Integrating Risk Management and Process Validation. Medical Device Congress Harvard – March 2007 Jim Handzo – Senior Manager QA Innovative Spinal Technologies Fran Akelewicz – Principal Practical Solutions . Agenda.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Lessons Learned in Integrating Risk Management and Process Validation' - erasmus


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
lessons learned in integrating risk management and process validation

Lessons Learned in Integrating Risk Management and Process Validation

Medical Device Congress

Harvard – March 2007

Jim Handzo – Senior Manager QA

Innovative Spinal Technologies

Fran Akelewicz – Principal

Practical Solutions

agenda
Agenda
  • Optimizing the validation activities sequence using risk management
  • Determining the statistical approach and acceptance criteria based on risk
  • Maximizing test plans and resources
approach
Approach
  • For illustration purposes we will use an example of:
    • Safety product

(functional approach)

New feature -a collar with a hinged rectangular plastic guard which will clip over the needle after use to prevent the user from getting stuck with the needle

key questions for process validation
Key questions for process validation
  • What are the important design characteristics?
  • Where and how are they impacted in the process?
  • What resources do I need?
  • What do I do first?
  • How should I conduct the validation?
  • What do I do if I don’t like the answer?
what are the important design characteristics
What are the important design characteristics?
  • Product inputs to process validation
    • Key design features
    • Residual risk profile (dFMEA)
    • Controls for the risk-prioritized design features
what are the important design characteristics7
What are the important design characteristics?
  • Product Inputs (User and Patient)
    • Key Design Features
      • Tools
        • Customer Requirements Matrix
        • Design Requirements Matrix
what are the important design characteristics8
What are the important design characteristics?
  • Product Inputs (User and Patient)
    • Customer Requirements Matrix
      • Focused on user needs
      • Focused on business needs
what are the important design characteristics9
What are the important design characteristics?
  • Product Inputs (User and Patient)
    • Design Requirements Matrix
      • Focused on risk analysis
what are the important design characteristics10
What are the important design characteristics?
  • Product residual risk profile
    • Without safety feature

X

what are the important design characteristics11
What are the important design characteristics?
  • Product residual risk profile
    • With safety feature

X

where and how are key design features impacted in the process
Where and how are key design features impacted in the process?
  • Process Inputs
    • Determine process control points that potentially impact the design features
      • Are process control points
        • One to one?
        • One to many?
        • Many to one?
    • Determine residual risk impact (pFMEA, FTA, etc.)
where and how are key design features impacted in the process13
Where and how are key design features impacted in the process?
  • Determine various process points that potentially impact the design feature
where and how are key design features impacted in the process14
Where and how are key design features impacted in the process?
  • Determine if the control points are
    • One process point to one design feature
    • One process point to many design features
    • Many process points to one design feature
where and how are key design features impacted in the process15
Where and how are key design features impacted in the process?
  • Use tools to characterize process outputs vs. design features
    • Design of Experiments (DOE)
    • Edge of Failure (EOF) Studies
    • Ranging Studies
    • Mean Time between Failures (MTBF)
    • Cpk vs. Ppk
  • Determine process residual risk
    • Process Map & pFMEA
    • FTA
    • Waterfall with Feedback Loop
    • EN 60601-1-4 PEMS “V” Diagram
where and how are key design features impacted in the process16
Where and how are key design features impacted in the process?
  • Process residual risk profile
    • Changes probability, not severity

X

what resources do i need
What resources do I need?
  • Dependent on type of product and/or process being evaluated
  • Electrical Engineer
    • Software Engineer
    • Reliability Engineer
    • Quality Engineer
  • Commensurate with the degree of residual risk
what do i do first
What do I do first?
  • Develop Process Validation Priority Risk Chart
    • Similar methodology to Product Risk Chart
    • Process effects on product are rated based on their impact
      • Safety
      • Performance
      • Acceptance
      • Compliance
      • Verification
  • Can also be used to develop a company Validation Master Plan
process map
Process Map
  • Formation and attachment of needle guard with collar attachment
what do i do first20
What do I do first?
  • Process Validation Priority Risk Chart
what do i do first21
What do I do first
  • Apply to
    • Entire processes
    • Sub-processes (then add)
what do i do if i don t like the answer
What do I do if I don’t like the answer?
  • Have a “Plan B”
    • Identify assignable causes
      • Justify discounting results with great care
    • Revisit assumptions made during validation setup
    • Revisit probabilities assigned to key design features
      • But you cannot change severity unless you change the design
  • Define contingencies in acceptance criteria
determining acceptance criteria
Determining acceptance criteria
  • Document in company policy
    • Similar to product risk chart
  • Key elements derived from product risk chart
    • Severity drives confidence levels
    • Confidence levels and probability drive sampling plans
      • Qualitative probabilities (Frequent, Probable, etc.) must be expressed quantitatively
      • Sampling plans should be discriminating enough to detect defects that relate to high severity/frequently occurring hazards
determining acceptance criteria26
Determining acceptance criteria
  • Acceptance Criteria Risk Chart
sampling plan determination
Sampling plan determination
  • Determine the operating characteristic (OC) curve of selected sampling plan
    • Incorporate quantitative probabilities
    • Determine acceptable errors
      • Type I (Producer’s Risk) – we say it’s bad when it’s not
      • Type II (Consumer Risk) – we say it’s good when it’s not
      • Does it match residual risk and probability?
sampling plan determination28
Sampling plan determination
  • Determine how much risk (error) you can tolerate in your estimates
    • Attributes
      • Percent defective error tolerance
    • Variables
      • Error tolerance of the average
  • Must constantly weigh sample size vs. estimate risk (error)
    • Economics vs. certainty
sampling plan determination30
Sampling plan determination
  • Use appropriate probability distributions when determining sampling plans
    • Binomial
      • Large populations
      • Sampling with replacement
    • Hypergeometric
      • Small populations
      • Sampling without replacement
sampling plan determination33
Sampling plan determination
  • Sampling Calculators available for download at:

www.devicecongress.com/agenda/day2.html

(Once on the website, go to Track A, 4:10pm session, for links to presentation materials. Calculators are in the excel document.)

maximizing test plans and resources
Maximizing Test Plans and Resources
  • Identify resources based on risk
  • Prioritize the process validation activities based on risk
  • Choose the acceptance criteria
  • Choose the appropriate sample methodology to minimize the business risk
change control
Change Control
  • Once process validation is completed you have established a “state of control”
  • Any changes made should consider:
    • Impact to product design risk (design verification testing; design validation testing)
    • Impact to process design risk (equipment design decisions)
    • Impact to control of risk within process
conclusions
Conclusions
  • Risk management in process validation:
    • Provides the opportunity to:
      • challenge existing assumptions
      • “think out of the box”
    • Acknowledges the risks that we have taken (product and business)
    • Provides a common language
    • Provides a framework for consistency
    • Formalizes what we have done
    • Contributes to safer products
thank you
Thank You !

Jim Handzo

Innovative Spinal Technologies

+1 508 452-3517

jhandzo@istspine.com

www.istspine.com

Fran Akelewicz

Practical Solutions

+1 215 337-9238

franakelewicz@comcast.net

www.practicalsolns.net