The Birchview Place Surface Water Control Structure Rehabilitation Project includes rehabilitating the existing M-3 structure with an approved budget of $483,500. This project, located at Birchview Place, prioritizes the establishment of water control structures. The recently completed R-1 project at Royal Palms Parkway and Belle Terre Boulevard serves as a reference. The M-3 project timeline includes substantial completion in May-June (90 days) and final completion in June-July (30 days).
E N D
M-3 Surface Water Control Structure Rehabilitation M-3 existing structure Artist rendering of finished M-3 structure
Revenue M-3 Weir Budget $467,500 Land Budget Transfer $16,000 Revised Budget $483,500 Expenses Cline M-3 Bid $439,325 Water Main Relocation $18,480 5.5% Contingency $25,695 $483,500
Notice to proceed February Substantial completion May - June (90 days) Final completion June - July (30 days)
Recently completed R-1 (Royal Palms Parkway and Belle Terre Boulevard) Project Artists rendering of M-3 Finished Project