Lower Lynn Town Centre Implementation Plan Update. OCP Implementation Committee Meeting March 6, 2013. Presentation Purpose and Outline. Purpose - update on the LLTC Implementation Plan and engagement process - seek feedback on opportunities to enhance the engagement process Outline

Download Presentation

Lower Lynn Town Centre Implementation Plan Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lower Lynn Town CentreImplementation Plan Update OCP Implementation Committee Meeting March 6, 2013

  2. Presentation Purpose and Outline Purpose - update on the LLTC Implementation Plan and engagement process - seek feedback on opportunities to enhance the engagement process Outline • Overview of OCP land use and policy re the LLTC • Vision and Concept Plan for LLTC • Planning and engagement process and timelines • Discussion

  3. LLTC – OCP Land Use and Policy Directions

  4. Vision for Lower Lynn Town Centre • Create a new town centre for Lower Lynn that: • Is a mixed use, transit-oriented community • Has a vibrant community focal point • Preservesthe industrial/employment areas • Enhances the multi-modal transportation network • Facilitates access to the frequent transit network • Strengthenscommunity connectivity • Facilitates a mix of housing types and neighbourhood revitalization • Establishes a strong community identity with a robust public realm • Enhances livability and social well-being through provision of public amenities • Promotesenvironmental protection • Integrates green infrastructure, energy efficiencies and alternative energy sources towards a more sustainable community Implement LLTCpolicies and design guidelines in development application review LLTC Implementation Plan LLTC Design Guidelines

  5. Lower Lynn Urban Design Concept Bridgman Park Seylynn Park Lynn Creek Crown Street Orwell Street Mountain Highway Main Street Phibbs Exchange

  6. Key milestones – LLTC implementation planning process Implement LLTCpolicies and design guidelines in development application review LLTC Implementation Plan LLTC Design Guidelines

  7. Summary of Consultations on the LLTC We are here Implement LLTCpolicies and design guidelines in development application review LLTC Implementation Plan LLTC Design Guidelines • Note: partnership with Vancouver Coastal Health

  8. Steps to Completion of LLTC Implementation Public and stakeholder engagement Council Consideration and Approvals Process Draft Implement Plan policies Draft Design Guidelines Implement LLTCpolicies and design guidelines in development application review Concept Plan LLTC Implementation Plan LLTC Design Guidelines Jan 2013 Feb - April 2013 Early Spring 2013 Late Spring 2013

  9. Tentative plan for public engagement (mid-April 2013)

  10. IDENTITY DNV 2030 | Lower Lynn Town Centre DISCUSSION • Suggestions for enhancing LLTC engagement process? • Suggestions re meeting format? • Suggestions re process for collecting feedback? • Suggestions re community outreach?