EC Integration Schedule

EC Integration Schedule. ~ 2 months delay. Stack B (EC C). Start stacking New target dates: B: 17 May A: 31 May. Stack B (EC A). Stack A (EC C). 8-planes at CERN. IDEAL DELIVERY OF FE to equip 8p as we stack We assume ~10 w.d. for installation and data acquisition per 8- 16-plane

cvilla
Download Presentation

EC Integration Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EC Integration Schedule ~ 2 months delay Stack B (EC C) Start stacking New target dates: B: 17 May A: 31 May Stack B (EC A) Stack A (EC C) M. Capeans

  2. 8-planes at CERN IDEAL DELIVERY OF FE to equip 8p as we stack We assume ~10 w.d. for installation and data acquisition per 8- 16-plane 6.06 ----- 8p B1 9.07 --- 8p B2 9. 08 ---- 8p B3 30.06 --- 16 p A1 10.08 --- 16p A2 3x 8p B 2x 16p A M. Capeans

  3. Next delivery of wheels by mid July 3x 8p B 3x 8p B 2x 16p A 2x 16p A M. Capeans

  4. Complete schedule FE delivery(Stacking delay is recovered in next delivery, by mid July: EC meets TC dates) 23 d 30 d M. Capeans