An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBDS commissioning – MKD tests Viliam Senaj, 11/12/2013

  2. MKD/B2 tests • HV tests (up to 5 TeV) without major problems: • noisy Trigout on Gen. H (up to 5V noise signal) – replaced chassis with PTU&PTC • Noisy output on one PTU of Gen. D – replaced PTU • Triax cable connectors on Gen. B – difficult to insert – replaced cables • Triax cable and 3 kV HV PS cable not fully inserted on Gen. E (27/11) • No abnormal sparking activity observed - surveillance of retriggering pick-ups Cts2a&b – with the same settings for all generators • DC 7TeV test: erratics on B (3 erratics 2 GTOs broken), D (6 erratics no damage), G (1 erratic no damage), J (3 erratics 2 GTO broken), N (2 erratics no damage) • 48 hours ramp test: 10min 400 GeV; 10 min ramp to Emax; 90 min at Emax and (12h 6.5 TeV, 12h 6.75 TeV, 24h 7 TeV) - OK (without B&J)

  3. Spontaneous firing of MKD/B2

  4. Spontaneous firing of MKD/B2

  5. Spontaneous firing of D/B2 on 16/11 02:13:06

  6. Spontaneous firing of D/B2 on 16/11 02:13:06

  7. Spontaneous firing (?) of B/B2 on16/11 20:41:10

  8. Spontaneous firing of B/B2 on16/11 20:41:10

  9. Spontaneous (?) firing B/B2 during switching off D/B2 18/11

  10. Erratic of B/B2 during switching off D/B2

  11. Non typical self-firing (?) of G/B2

  12. Searching reasons of spontaneous firing • Abnormally dry air observed in UA67 during tests (dew point - 9 deg) • To find if it affects B1 – it was put in DC mode between 30/11-03/12: ~24h rising from 6 to 7 Tev; 36 h at 7 TeV and finally 24 h at 7.1 TeV; no self-firing observed

  13. Searching reasons of spontaneous firing • Hypothesis of charging of plexiglass insulation rods by friction of dry air blown by ventilators towards GTO stacks: switched off ventilators in Gen D, E, F, G, H, I, J – during 7 days – not confirmed • Observation of noisy output of several PTU – even PTU signal before GTO current – on Gen. D:

  14. Continuation tests • Generators B and J in laboratory for tests • DC test during Christmass • DC and ramp test in 2014 • Surveillance of PTU activity/retrigger propagation (thresholding)