100 likes | 232 Views
This report outlines the performance and testing results for upstream and downstream magnets, including dipole (B1, B2) and quadrupole (Q1-Q9) systems. Completed tests on the upstream dipole B1 and quadrupoles Q1-Q3 indicate satisfactory performance to 250A, with critical electrical and functional tests prior to installation. Future tests are scheduled for January 2008, focusing on polarity, reproducibility, and hysteresis. Preliminary assessments for downstream magnets are set to begin, with an emphasis on identifying any issues early in the process.
E N D
Magnet field testing • Upstream magnets:- Dipole B1 Quadrupoles Q1-Q3 • Downstream magnets:- Dipole B2 Quadrupoles Q4-Q9 Kevin Tilley, Paul Flower, Mark Rayner , Henry Nebrensky, 16th November
Upstream dipole – B1 – completed tests • Upstream dipole critical to extract beam from synchrotron vault. • Performed functional tests prior to installation in July. • Performed electrical/water tests (AN talk) Measurements agreed perfectly with tables & theory (Leff) to 250A. Not tested to full field. Central field versus current to250Amps. Field map & L_effectiveas expected
Upstream dipole – B1 – future tests • Polarity in situ • Full B.v.I tests (into saturation) • Determine rqd reproducibility (B/I) • Measure hysteresis • & complete standardisation if rqd. • Scheduled for w/c 14th Jan’08 • May monitor the field of this measurement directly during running if hysteresis significant. • Note, some discussion about changing pole tip of this magnet for non-tapered pole (homogeneities) – use same tests
Upstream quadrupole – Q1 – completed tests • Performed functional tests prior to installation in July. • Performed electrical/water tests (AN talk) • Measured g.v.I, hysteresis • Measured (g, magnetic centre, skew)
Upstream quadrupole – Q1 – completed tests • Jig allows measurement of field relative to mechanical centre & known rotation – survey references. • Sample field along 3 lines -> extract 4 parameters, then solve for (g,magnetic centre(x,y), skew). Errors in magnetic centre ~ ±0.1mm • no significant magnetic centre displacement • no significant skew. • g.v. I as expected. • hysteresis measured at ~0.5% • - magnet works ok.
Upstream quadrupoles – Q1-Q3 –future tests • Polarity in situ • Scheduled for w/c 14th Jan’08
Downstream dipole – B2 – future tests • Polarity in situ • Full B.v.I tests (into saturation) • Determine rqd reproducibility (B/I) • Measure hysteresis • & complete standardisation if rqd. • Scheduled for w/c 9th Jan’08 or early December if services available.
Downstream quadrupoles – Q4-Q9 – present tests • Perform basic tests.…to qualify as early as possible if any problems exist.… • Pole tip fields to determine ~g.v.I • Field balance on each pole tip / colloid. • If indications, potential to perform detailed checks with jig. • Expected to begin this week, turnaround time <1week per magnet.
Downstream quadrupoles – Q4-Q9 – present tests • We have only incomplete field specifications for the Q35s! • Detailed tests on at least two Q35s complete with mirror plates. • Measure one magnet with each of the two coil types for reference data. • L_effective. • Adaptor & jig -> detailed (g,magnetic centre(x,y), skew) as before. • g.v.I • Determine required reproducibility. • Hysteresis. • Standardisation if required. • In ~2-3weeks
Summary. • Upstream magnets:- Dipole:- performs well to 250A. Checks of full current, polarity, hysteresis in situ. w/c Jan 14th Quadrupoles: one magnet tested – performs well. Polarity of all in situ. w/c Jan14th. • Downstream magnets:- Dipole:- to be tested early December or w/c Jan 9th. Quadrupoles: basic testing schedule commencing this week. Detailed measurements on at least two of differing coil types for reference data.