1 / 30

Chapter 7 Capacity Planning and Management

Chapter 7 Capacity Planning and Management. Capacity Planning and Management. Capacity planning and management addresses two managerial problems: Matching capacity to plans –by either providing sufficient capacity to execute the plan or adjusting the plan to meet available capacity.

bohnert
Download Presentation

Chapter 7 Capacity Planning and Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 7Capacity Planning and Management

  2. Capacity Planning and Management Capacity planning and management addresses two managerial problems: Matching capacity to plans–by either providing sufficient capacity to execute the plan or adjusting the plan to meet available capacity. Consider the marketplace implications of faster throughput times–at the expense of reduced capacity utilization.

  3. Role of Capacity Planning in MPC • The primary objective of capacity planning techniques is to estimate capacity requirements early enough to be able to meet those requirements • Flawless execution of the capacity plan allows the firm to avoid unpleasant surprises • Insufficient capacity leads to deteriorating delivery performance • Excess capacity may be a needless expense

  4. Capacity Planning in the MPC System Resource planning Sales and operations planning Demand management Long Range Resource planning Master production scheduling Rough-cut capacity planning Medium Range Detailed material planning Capacity requirement planning Material and capacity plans Short Range Finite Loading Shop-floor systems Supplier systems Input/output analysis

  5. Links to other MPC System Modules

  6. Capacity Planning Using Overall Factors (CPOF) • Simplest rough-cut capacity planning approach • Data inputs from master production schedule • Based on planning factors from historical data (work center utilization, production standards) • Overall labor- or machine-hour capacity requirements are estimated from MPS data • Estimate is allocated to work centers based on historical workloads • Inherent inaccuracies may limit usefulness

  7. CPOF Example Total required capacity = (33*0.95)+(17*1.85) = 62.80 Work center capacity = Historical percentage*Total required capacity

  8. Capacity Bills • Rough-cut capacity planning method that provides more direct link to individual end products • Bill of capacity indicates total standard time to produce one unit of an end product (by work center) • Master production schedule data is then used to estimate capacity requirements for each work center • Requires more data than CPOF procedure

  9. Capacity Bill Example Total hours include both std. run time and std. setup time Std. Setup hours are spread over the standard lot size

  10. Capacity Bill Example MPS quantities are multiplied by bill of capacity to determine work center capacity requirements by period

  11. Resource Profiles • Rough-cut capacity planning technique that includes production lead time information • Provides time-phased projections of capacity requirements for individual work centers • More sophisticated approach but requires tracking of relatively short time periods (< 1 week)

  12. Resource Profile Example Production of one unit of product A in period 5 requires production activity in periods 3, 4, and 5 and in work centers 100, 200, and 300

  13. Resource Profile Example Requirements (by work center and period) for one unit of end product are multiplied by the MPS plan to determine capacity requirements These requirements are then summed over all periods to finalize the process

  14. Capacity Requirements Planning (CRP) • Capacity requirements planning differs from the rough-cut planning procedures • Utilizes time-phased material plan from MRP • Takes into account materials in inventory • Accounts for the current status of work-in-process • Accounts for service parts and other demands not accounted for in the MPS • Requires more inputs and more computational resources

  15. Capacity Requirements Planning Example Detailed MRP Data Scheduled/planned quantity multiplied by processing time for work center This process is repeated for each work center to complete the plan

  16. Scheduling Capacity and Materials Simultaneously • Capacity requirements planning doesn’t consider capacity when planning materials • Assumes that capacity can be adjusted, given sufficient warning • Planning capacity and materials at the same time allows construction of a plan that works within current capacity constraints

  17. Finite Capacity Scheduling • Simulates job order start and finish times in each work center • Establishes a detailed schedule for each job in each work center • When a work center’s capacity is not sufficient for all planned jobs, prioritization rules determine which jobs will be shifted to later times

  18. Finite Capacity Scheduling Product A does not consume all available capacity Combination of all products consumes all available capacity in several periods Planned orders are shifted to stay within capacity limitations

  19. Work Center Scheduling • Vertical Loading–each work center is scheduled job by job without consideration of other work centers • Increases capacity utilization but may result in more partial job completion • Horizontal Loading–jobs are scheduled through all work centers in order of priority • Lower capacity utilization but generally a higher proportion of jobs are completed in a shorter time span (higher customer service levels)

  20. Finite Capacity Scheduling • The FCS plan is a simulation • Randomness leads to actual times that don’t match scheduled times • Should the work center wait for a job that isn’t available on time (idleness = lost capacity) • Over time, the accuracy of the plan deteriorates • Frequent rescheduling may be needed to maintain accuracy • Rescheduling process is computationally expensive

  21. Advanced Production Scheduling (APS) • Expands Finite Capacity Scheduling to the entire product structure (end products and sub-assemblies) • Can lead to a significant reduction in lead times • Requires accurate scheduling parameters, flawless execution, and prompt recovery from any problems

  22. Capacity Management

  23. Capacity Monitoring with Input/Output Control • Planned inputs are determined by the capacity planning process • Planned outputs depend upon the nature of the work center • Capacity-constrained–planned output is determined by the processing rate of the work center • Non-capacity-constrained–planned outputs match planned inputs • Differences between plan and actual must be addressed (management by exception)

  24. Capacity Planning in the MPC System • Short-term capacity planning problems can be reduced by well-executed production and resource planning • Efficient use of sufficient capacity by a good shop-floor system reduces capacity issues

  25. Choosing the Measure of Capacity • Capacity can be measured in many ways • Labor hours, machine hours, physical units, monetary units • The firm’s needs and constraints should determine the capacity measure • Trends • Shrinking portion of direct labor • Less clear distinctions between direct and indirect labor • Reduced ability to change labor capacity • Outsourcing • Flexible automation/cellular technologies

  26. Using the Capacity Plan • Two broad choices are available when actual capacity and plan are mismatched • Change capacity–reduce or increase capacity as indicated (within constraints) • Revise material plan–change requirements and/or timing to match available capacity • The amount of material that can be produced is limited by the available capacity, regardless of the material plan

  27. Principles • Capacity plans must be developed concurrently with material plans if the material plans are to be realized. • Capacity planning techniques must match the level of detail and actual company circumstances. • Capacity planning can be simplified in JIT environments. • Better resource and production planning processes lead to less difficult capacity planning processes. • Better shop-floor systems reduce the need for short-term capacity planning.

  28. Principles • More detailed capacity planning systems demand more data and database maintenance. • When capacity does not match the requirements, it isn’t always capacity that should change. • Capacity must be planned, but use of capacity must also be monitored and controlled. • Capacity planning techniques can be applied to selected key resources. • Capacity measures should reflect reasonable levels of output from key resources.

More Related