california advanced services fund approval process resolution t 17143 item 33 l.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
California Advanced Services Fund Approval Process Resolution T-17143 Item 33 PowerPoint Presentation
Download Presentation
California Advanced Services Fund Approval Process Resolution T-17143 Item 33

Loading in 2 Seconds...

play fullscreen
1 / 5

California Advanced Services Fund Approval Process Resolution T-17143 Item 33 - PowerPoint PPT Presentation


  • 94 Views
  • Uploaded on

California Advanced Services Fund Approval Process Resolution T-17143 Item 33. Commission Meeting June 12, 2008. Background of the California Advanced Services Fund (CASF) D.07-12-054 established the CASF to provide rural communities access to broadband

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

California Advanced Services Fund Approval Process Resolution T-17143 Item 33


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
california advanced services fund approval process resolution t 17143 item 33

California Advanced Services FundApproval ProcessResolution T-17143Item 33

Commission Meeting

June 12, 2008

slide2
Background of the

California Advanced Services Fund (CASF)

  • D.07-12-054 established the CASF to provide rural communities access to broadband
  • $100 million is available for qualifying projects over a 2-year period
  • Provides matching funds up to 40% of the total project cost; recipient provides 60%
  • Priority for funding is to award money for Unserved Area project proposals
  • Funding is available to PUC-registered telephone corporations
slide3
Major Milestones -
    • February 7, 2008 – CD held a technical workshop to discuss a draft template (“straw man”) on application requirements and scoring criteria for proposed CASF projects
    • February 25, 2008 – CD distributed a preliminary draft workshop report to workshop participants
    • March 7, 2008 – CD submitted the final workshop report to the Assigned Commissioner
    • March 13, 2008 – ACR Releasing the Final Workshop Report on the CASF served to parties in the R.06-06-028 proceeding
slide4

Today’s Resolution T-17143 –

    • Lays out the Requirements, Timelines, and Scoring Criteria for parties to qualify for project funding
    • Scoring Criteria of:
      • Funds Requested per Potential Customers 40 pts
      • Speed 20 pts
      • Service Area 15 pts
      • Timeliness of Completion of Project 5 pts
      • Pricing 10 pts
      • Guaranteed Pricing Period 5 pts
      • Low-Income Areas 5 pts

100 pts

slide5
The Award Process Begins!

The Application Timelines for

Unserved and Underserved areas:

  • 1st Wave: Unserved Areas - July 24, 2008 filing date
    • Approved Projects without challenges or counter proposals will be set for the Commission’s Meeting of November 21, 2008
    • Approved Projects with challenges or counter proposals will be set for a January 2009 Meeting
  • 2nd Wave: Underserved Areas - August 25, 2008 filing date
      • Expect these Resolutions to be on the February and March 2009 Agendas