1 / 32

n-3He Project Technical Review 2013: Experiment Design & Execution

Detailed technical review of n-3He project by University of Kentucky for n-3He Collaboration, covering experiment design, setup, execution, resources, and collaboration aspects. Discussion on experiment layout, manpower, and scheduling.

azuka
Download Presentation

n-3He Project Technical Review 2013: Experiment Design & Execution

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The n-3He Project Christopher Crawford University of Kentucky for the n-3He Collaboration n-3He Technical Review ORNL, TN 2013-01-08

  2. Outline • Experiment design • Reaction and observable • Experimental setup • Execution • Commissioning plan– 2 configurations • Run time • Resources • Collaboration • Organization • Manpower • WBS subpackages • Beam line • Solenoid • Spin rotator • Target / detector • Preamplifiers • Data acquisition • Online analysis • Integration • Commissioning

  3. Experimental setup Measure PV spin asymmetry A ~ 1x10-7sn  kp(Viviani) 15% relative error longitudinal holding field – suppressed PC nuclear asymmetry A=1.7x10-6(Hale) sn  kn x kpsuppressed by two small angles RF spin flipper – negligible spin-dependence of neutron velocity 3He ion chamber – both target and detector supermirror bender polarizer (transverse) FnPB cold neutron guide 10 Gauss solenoid 3He Beam Monitor RF spinrotator 3He target / ion chamber FNPB n-3He

  4. Experimental Layout – from NPDGamma …

  5. Experimental Layout – … to n3He

  6. Experimental Layout – … to n3He Even though NPDG and n3He are very similar, we still require two separate IRR’s for n3He

  7. Unistructure support – preliminary CAD model TOP VIEW

  8. Unistructure support – preliminary CAD model SIDE VIEW

  9. n-3He collaboration • Spokespersons D. Bowman, M. Gericke, C. Crawford • Local Project Manager S. Penttila • Project Engineer Jack Thomison • Work Subpackage Leaders G. Greene Neutronics L. Barrón Solenoid C. Crawford Spin rotator M. Gericke Target / detector D. Bowman Preamplifiers C. Crawford Data acquisition N. Fomin Online analysis J. Hamblen Integration D. Bowman Commissioning

  10. Neutronics for the experiment

  11. Neutronics for the experiment • Scope • FnPB guide, polarizer, beam monitors – stays UNCHANGED • PPS remains UNCHANGED • Beam profile scanners, polarimetry • Status • All equipment is being used for NPDG experiment except the beam profile scanners • XY-scanners in hand and tested • Remaining work • Design shielding and mounts for xy-scanner – April • Design mount for 3He analyzer (polarimetry) – April • Modify beamline shielding – April Chris Hayes,Kabir LatifulJosh Hamblen Geoff Greene

  12. Magnetic field

  13. Magnetic field • Scope • Magnetic field simulations to verify adiabatic spin rotation and uniformity • Unistructure frame for Magnetic coils, Spin rotator, and Target/detector mounts directly onto existing NPDG stands on the beamline • Design, construction, and testing of longitudinal solenoid 10 Gauss holding field, just like NDPG • Status • Conceptual design, preliminary calculations indicate adiabaticity 15 coils, 15 cm apart, 35 cm radius, 150 A turns • Materials for frame and coil supports are in hand • Remaining work • Machining of coil supports: January – March • Assembly of coils and stand: April • Test coils and mapping of field at UNAM: May Andrés Ramirez, Libertad Barrón

  14. Spin rotator

  15. Spin rotator • Scope • Design of RF double cos-theta coil • Machining forms for inner/outer coils, aluminum enclosure, mounts • RF driver electronics • Field mapping and testing • Status • Design complete • Machining of coil forms near completion • RF driver electronics exist and are being used for NPDG • Remaining work • Winding of coils: January • Construction of enclosure: Jan (in parallel) • Testing and field mapping: Jan–Feb (in parallel) Chris Hayes, Geoff Greene Chris Crawford

  16. Inner Cylinder Design: Complete Construction: In progress at UT Physics machine shop. Scheduled completion date: January 2014.

  17. Outer Coils Design: Complete Construction: Outer coils fabricated using 3D print Technology. Delivered 2014-01-03

  18. Aluminum Shell Design: Some design issues are still in progress including a moveable stand for precision alignment with neutron beam. Construction: Aluminum shell will be built by UT physics machine shop end of January

  19. Target / detector

  20. Target /detector • Scope • Vacuum enclosure with 1 atm 3He • 144 channels of sense wires • Status • Vacuum enclosure in hand • Wires soldered to frames • Remaining work • Assemble wire plane stack, readout plane: Feb – March • Vacuum test and fill with 3He: March • Electronics noise testing April Mark McCrea Michael Gericke Seppo Penttila

  21. Target /detector: vacuum housing • 12” Conflat end flanges • 1 mm Al windows • Fill gas: 1 atm 3He • Feedthroughs: 4x signal, 2x high voltage, 2x vacuum

  22. Target / detector: ion chamber wire planes • 17 HV planes • 16 signal planes • 144 signal wires • All wires soldered to frames • Mounting hardware and fittings all constructed • PCB readout boards willarrive late January • Assembly in February • Testing starting in March

  23. Preamplifiers Kabir Latiful Irakli Garishvili David Bowman • Scope • 4 boxes of 36 channels: one per vacuum feedthrough • Circuit board designed locally at ORNL • Connector to ion chamber vacuum port and cabling to DAQ module • Status • Circuit boards constructed and initial testing complete • Achieved theoretical limit on some channels, testing in progress • Remaining work • Design forced air cooling • Build cables to preamp • Test all channels • Test instrumentalasymmetries withspin rotator, target

  24. Data acquisition Kabir Latiful Irakli Garishvili Nadia Fomin Chris Crawford • Scope • 144 channels of 24 bit, 128 KS/s ADC • Standalone system: NO support from DAQ group • Progress • PO to be issued for data acquisition electronics next week – delivery of hardware end of March, firmware upgrade end of May • Basic control software written; used to take and analyze data • Preliminary measurements of electronic noise – within specification • Remaining work • Build cabling from preamps to DAQ: Jan • Test complete system: Feb – April

  25. Online Analysis Kabir Latiful Irakli Garishvili Carlos Olguin Ivan Novikov Nadia Fomin Michael Gericke Chris Crawford • Scope: • Data transfer and analysis computers • 36 TB RAID storage • Online analysis software • STAND-ALONE system – no support required from DAQ group • Status: • NPDG infrastructure • Existing software • Schedule forward: • Build complete network – March • Production-gradesoftware – April

  26. Integration / preassembly • Scope: • Design of unistructure support frame • Design, construction of mountingand alignment hardware • Maintain 3d solid model of experiment • Status: • Preliminary solid model exists • Conceptual design for mounts and alignment • Remaining work: • Final design of stand and mounting / alignment: Feb • Construction of mounting, alignment hardware: Apr • Assembly of complete system: May-June • Dry run of commissioning process: June Caleb Wickersham Mark McCrea Jack Thomison Geoff Greene Josh Hamblen

  27. Alignment • Mounting / alignment components • Aperture / crosshairs for beam scan • Support stand and xy-adjustment for theodolite • Alignment V-block for trimming B-field • Optical system and adjustable mount for target • 10 mrad tolerance – no need for S/A crew

  28. Commissioning • Scope: • Testing for instrumental asymmetries • Dry run of commissioning during assembly • Polarimetry and beam scans • Alignment of beam / magnetic field / chamber • Measurement of parity-conserving asymmetry with transverse field • Status: • Preliminary commissioning plan well-thought out • Remaining work: • Installation in FnPB: July • Beam alignment scans: Aug-Sept PHASE 1 IRR • Measure transverse asymmetry: Oct–Dec PHASE 2 IRR everyone… David Bowman

  29. Installation – see Jack’s talk for more details

  30. Commissioning / run plan IRR #1 IRR #2 • Scan beam profile upstreamand transfer centroid to crosshairs • Scan beam profile downstream • Align theodolite to crosshairs • Align B-field to theodolite • Field map in RFSR/Target region • Align the position / angle of target with theodolite / autocollimator • Tune RSFR / measure polarization • Measure physics asymmetry

  31. Timeline – see Seppo’s talk for more details • Construction of subsystems in parallel • Will stage experiment in EDM building and performdry run of field map, beam map, and alignment procedures • Expect to be ready for beam at beginning of cycle Aug 2014 • Milestones • 2014-05-01 Begin integration on common stand • 2014-08-01 Begin installation in FnPB cave • 2014-10-06 IRR – begin commissioning phase • 2014-02-15 Begin physics data taking • Runtime • 66 days commissioning (all equipment pre-assembled) • 15 days PC transverse asymmetry 1.7 x 10-6 ± 0.6 x 10-7 • 208 days PV longitudinal asymmetry 1.2 x 10-7 ± 1.7 x 10-8* based on theoretical calculations

  32. Resources – see Jack’s talk for more details • Minimal utilization of SNS crafts • Most equipment mounted on single support structure,staged in the EDM building, craned onto NPDG det. Support • Machining will be done at university shops • only SNS engineer is Jack Thomison, on n3He funds– 3D solid model will be drafted within the collaboration,reviewed by Jack, and incorporated into SNS model • Minimal radiological group support– MCNP model created by Nadia Fomin, Paul Mueller, validated by radiation group • No survey & alignment resources required – alignment is relative to beam scan • No support required from DAQ group – standalone system

More Related