Agenda. Root Cause FrameworkFindingsPARCA Actions going forward. Root Cause: Framework. Cost, schedule and performance impact. Management. Unrealistic cost or schedule estimates. Unrealistic performance expectations. Inadequate risk assessment. Funding instability or inadequacy. Quantity change. U
E N D
2. Agenda Root Cause Framework
Findings
PARCA Actions going forward
3. Root Cause: Framework
4. Step One: Clarify What Happened Define the cost and/or schedule growth
Gather documentation
Program content and guidance
Acquisition documents
General background
Program chronology
Change analysis
Prepare for fact finding
5. Fact Finding & Analysis Interviews
Program Office and Contractors
Organizations providing functional support to program
Analysis of performance reporting data
EVMS
Cost reporting
Performance metrics
Program documentation, studies, reports
Exact analytical methods are case dependent
Blend of quantitative and qualitative (but fact based) methodologies
Decision-maker concerns
Actionability
Exogenous vs endogenous
Effectiveness
6. Products One-page memorandum for Nunn-McCurdy certification process
Describes breach and its root causes
Supporting document in the program certification package sent to Congress
Briefing summarizing results
Lessons for acquisition community
Reports
Analytical tools
Contribution for PARCA’s annual report to Congress
7. Summary of Findings
8. Unrealistic Cost and Schedule Estimates Mainly, the source of these problems is not un-professional or incomplete cost estimates, but rather bad programmatic assumptions
The criteria that PARCA uses is: “do the facts and DoD experience at the time of the estimate support the assumptions made?”
The F-35 is an illustrative example; bad postulates include:
That the state of design was far more mature than average;
That vertical lift, with CAD/CATIA / simulation tools, would be easier; and
That arbitrating multi-Service configurations requirements would be straightforward.
Challenging — and even recognizing — deeply held programmatic assumptions is difficult, but must be done at the milestone.
9. Improving EVM: Better Situational Awareness Tailored metrics
Relevant metrics e.g. identification AND tracking of “bets”
Effective metrics e.g. avoiding integration effects
Earned Value Management
Compliance
Effectiveness Integrated with PARCA’s program assessments
Semi-annual, statutory reviews after critical Nunn-McCurdy breach
As part of DAES process
10. Systems Engineering & Interface Management are a Major Challenge Complex process which demands SME input Two key questions
Does Government know what it wants/able to define it ?
Is schedule based upon engineering realities?
11. Effective Contracting Strategy Two elements
Blocking and tackling
Incentive strategy effectiveness Incentive evaluation
Aligned with program goals and challenges
Demanding yet achievable
Sufficient to motivate
No perverse effects
Consistent with overall incentives
Signal sent and received
12. Going Forward: Quantity-Related Sources of Variance Every quantity change is in response to something else.
The criteria that PARCA uses is: “is the underlying principal animating source of the quantity change endogenous or exogenous to the operation of the acquisition system?”
Changes induced from doctrinal or “pure” fiscal constraints are outside
However, changes that are in recognition to, for example, escalating unit costs or schedule slips, are properly chargeable to the acquisition system
Findings to date: half of the six Root Causes in which quantity was a principal factor stem from “internal” reasons, and half “external.”
There will always be some debate about this, but PARCA is prepared to stick by its assessments
13. Earned Value Management (EVM) Status
Reconstituted OSD EVM IPT
Membership from: OSD, Services, Intel Community, DCMA, DCAA, DAU.
Chartered to develop and coordinate EVM items common across DoD, and coordinate and provide service level concurrence on OSD EVM positions on policy and guidance.
Created PARCA EVM Stakeholders Initiative
Forum for Industry Stakeholders to provide comments and recommendations to PARCA on EVM issues which impact the wider EVM community.
Current issues: CPR Data Reporting, Integrated Master Schedule, Access to EVM Data (NDA Process).
Transitioning EVM Central Repository from CAPE to PARCA.
14. PARCA Evolution in 2011 Work related to 2009 WSARA
Further evolution of Performance Assessment institutions and guidance implementation
Bringing on-line innovative tools for the acquisition enterprise to use
Feeding back Root Cause lessons into routine acquisition practice
Work related to the 2011 NDAA section 2548
Prepare detailed guidance and detailed instructions for the conduct of Performance Assessments within DoD
Reflect Performance Assessment activities, findings, and recommendations during the year
EVM
Complete migration of EVM duties to PARCA
New PARCA division: “Acquisition Policy and Institutional Analysis”
Purpose is to analyze the performance of DoD’s institutions and policies
A re-organization of USD(AT&L) will be announced shortly that will create and resource this division
15. Backup
16. Performance Assessment in 2010 PARCA is using the DAES process to execute its performance assessment responsibilities
Makes use of existing infrastructure
Provides venue for PARCA analysis and observations to be included in decision-making
PARCA has improved the DAES process in two ways:
Improving the quality of the analysis by actively participating in all parts of the process
Assessing individual programs
Choosing programs that brief to the DAES meetings
Ensuring that critical issues are addressed at DAES meetings
Briefing PARCA analyses and insights at DAES meetings
Suggesting specific changes to the DAES mechanism
Responded to PUSD(AT&L) request for recommendations to “…assure that PARCA’s functions comply with the statutory provisions of 2009 WSARA.”
Recommendations are now being refined and tested
17. Performance Assessment in 2010 PARCA has completed six statutorily required post-Nunn McCurdy performance assessments
F-35
RMS
DDG-1000
ATIRCM/CMWS
Apache Block III
WGS
PARCA completed two statutorily required Full Rate Production assessments
SSN-774
H-1 Upgrades
18. Root Cause Analyses in 2010 Performed seven root cause analyses as part of Nunn-McCurdy breach process
F-35
DDG-1000
ATIRCM/CMWS
Excalibur
Six root cause analyses are ongoing
Some “on request”
Variety of programs
RMS
Apache Block III
WGS
19. Ongoing Development Analytical methodologies
Impact of funding constraints in development
Evaluation of incentive strategies
Systems engineering assessment
EV metrics and data presentation Relationships
SME sources for specific issues
Knowledge-sharing of analytical approaches e.g. UK MoD
Effective use of root cause analysis results
Effective mechanisms for sharing lessons for benefit of acquisition community
20. Policies, Procedures, and Guidance State of play
WSARA 09 requires PARCA to address
Virtually no current guidance for root cause analysis
Other organizations have done some root cause analysis
Key questions exist e.g. is it enough to say that estimate was unrealistic (WSARA 09 category) or should we ask why?
Three different purposes
Documentation of PARCA processes
Service conduct of root cause analyses
Program Office conduct of root cause analyses
21. PARCA Root Cause Objectives Independence and even-handedness
Analysis transparently based on facts
Clear and accurate definition of the predominant issues
Actionable
Relevant trends
Timely results