slide1 l.
Download
Skip this Video
Loading SlideShow in 5 Seconds..
Robert Kondziolka Salt River Project Manager of Transmission Planning PowerPoint Presentation
Download Presentation
Robert Kondziolka Salt River Project Manager of Transmission Planning

Loading in 2 Seconds...

play fullscreen
1 / 3

Robert Kondziolka Salt River Project Manager of Transmission Planning - PowerPoint PPT Presentation


  • 368 Views
  • Uploaded on

Arizona Corporation Commission. Workshop. Fourth Biennial Transmission Assessment 2006 - 2015. Robert Kondziolka Salt River Project Manager of Transmission Planning. June 6, 2006 Phoenix, Arizona. Contingency Planning (N-1-1) For Palo Verde Transmission System Pre-2006 Summer Season.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Robert Kondziolka Salt River Project Manager of Transmission Planning' - JasminFlorian


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Arizona CorporationCommission

Workshop

Fourth Biennial Transmission Assessment2006 - 2015

Robert Kondziolka

Salt River Project

Manager of Transmission Planning

June 6, 2006

Phoenix, Arizona

slide2

Contingency Planning (N-1-1)For Palo Verde Transmission System Pre-2006 Summer Season

  • Facilities Out of Service: Fall 2005- June 1, 2006PaloVerde-Devers, Hassayampa-N.Gila, N. Gila- Imperial Valley 500kV Lines;4 Series Capacitors Banks and Westwing 500/230kV Transformer #4 Out of Service
  • Maximum Scheduling Generation Capacity: 6,107 MW (Will Meet the Expected Power Transfer Need)
slide3

Contingency Planning (N-1-1)For Palo Verde Transmission System Pre-2006 Summer Season

  • Facilities Back Into Service:- After June 1, 2006PaloVerde-Devers, Hassayampa-N.Gila, N. Gila- Imperial Valley 500kV Lines;4 Series Capacitors Banks and Westwing 500/230kV Transformer #4 Back into Service
  • Maximum Scheduling Generation Capacity: 7,457 MW (Will Adequately Meet Power Transfer Requirement)*