High Bandwidth Transverse Feedback Budget and Manpower

High Bandwidth Transverse Feedback Budget and Manpower. Kicker / PU prototype Split LARP/CERN Split phase 2 / Full SPS Project . W. Hofle . Kickers and PU . CERN man power estimate for prototypes (2013-2015)  4 FTE 2013: 0.35 FTE 2014: 1.9 FTE 2015: 1.75 FTE

uta
Download Presentation

High Bandwidth Transverse Feedback Budget and Manpower

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. High Bandwidth Transverse FeedbackBudget and Manpower • Kicker / PU prototype • Split LARP/CERN • Split phase 2 / Full SPS Project W. Hofle

  2. Kickers and PU • CERN man power estimate for prototypes (2013-2015)  4 FTE • 2013: 0.35 FTE • 2014: 1.9 FTE • 2015: 1.75 FTE 2 FTE mechanical engineering covered by VIA request 0.6 FTE staff technician, post requested by GL to DH 1.4 FTE: existing • FSU and Material for prototypes • 200 kCHFwith LIU for prototypes • Production (20162017) • 300 kCHF • Manpower for production depends on design changes required • Assume 0.5 FTE for 2016 and 2017 • From collaborations: Electromagnetic Design • Support from ABP Group and LNF-INFN for impedance calculation

  3. LARP support before 2017 • Electronics • R&D for demonstrator 2.0 for post LS1 MDs • evaluation of amplifiers • closed orbit suppression, phase compensation technics, delay alignment, synchronisation, in close collaboration with CERN • contingency at CERN needed if LARP funding before 2017 too low  involve CERN electronics designers now (visits at SLAC ?!) • at CERN 0.3 FTE / y, travel cost and stay at SLAC • Support for Controls Algorithms Conceptual Design from SLAC • matching manpower at CERN in ABP to support simulations (0.3 FTE / y) • MDs and analysis • Shared CERN / LARP effort • Need adequate support from BE-OP and BE-ABP (0.3 FTE / y) • BE-RF-FB MD support: 0.2 FTE / y CERN: 3.3 FTE, 150 kCHF

  4. Summary CERN resources before Full Construction Project launched • Already spent (cabling, electronics for PU) • ~ 200 kCHF • Kicker and PU prototype • 200 kCHF, 4 FTE • Amplifiers • 150 kCHF, 0.3 FTE • Demonstrator work for beam period between LS1 and LS2 • 150 kCHF, 3.3 FTE • Kicker production, needs resources before start of 2017 • 100 kCHF, 0.5 FTE in 2016 • TOTAL before construction launched: 800 kCHF, 8.1 FTE

  5. Status of Requests by LARP and LIU 4.470 MUS$ Revision needed pre-2017 12.275 MUS$ Total LARP estimate: 16.745 MUS$ includes man power estimate in US accounting standards for both CERN and US current LIU total for material 1593 kCHF no contingency no price escalation