IT-3675/GS Bidders’ Conference. Supply & Installation of Site Supervision (SUSI) Access Control Systems Presentation of the Technical Specification 3 September 2012. Introduction & Scope. This Call for Tenders concerns Supply & installation of Physical Access Control equipment such as:

Download Presentation

IT-3675/GS Bidders’ Conference

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


It 3675 gs bidders conference

IT-3675/GS Bidders’ Conference

Supply & Installation of Site Supervision (SUSI) Access Control Systems

Presentation of the Technical Specification

3 September 2012


Introduction scope

Introduction & Scope

This Call for Tenders concerns

Supply & installation of Physical Access Control equipment such as:

  • Road gates & barriers

  • Access control system, card readers and control units

  • Intercoms

  • ANPR systems

  • Key distribution systems

  • Off-line electronic locks

  • Video surveillance cameras & converters

    At CERN this equipment is commonly designated as SUSI

    an acronym for “SUpervision des SItes”

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Introduction scope1

Introduction & Scope

  • Deliveries are foreseen over

    • 5 years

    • with two optional extensions of 1 year

  • Works shall take place across ALL the CERN sites, both in :

    • France and in

    • Switzerland

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Firm selection criteria

Firm Selection Criteria

Type of Firms

  • A single firm with or without subcontractors

  • Proven competence as equipment integrators and installers

  • Capable of supplying and installing on the CERN sites

    Having been qualified by their reply to the Market Survey MS-3675/GS and by the onsite visits performed with CERN representatives.

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Contract organisation

Contract Organisation

  • Part 1

    • Deployment of a test platform (SUSI 0)

    • 6 months maximum

    • If unsuccessful  contract termination

    • If successful  Part2

  • Part 2

    • On-site installations & After-sales support

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Part 1 test validation

Part 1 – Test & Validation

Part 1 – Test & Validation Platform

  • Phase 1 – Preliminary Design

  • Phase 2 – Detailed Design

  • Phase 3 – Test Platform Deployment

  • Phase 4 – Production Deployment

    • Actually belongs in Part 2 but given here for coherence

    • Quoting of this element belongs to Part 2

      If Part 1 successful then :

      Part 2 – Onsite Installation & After Sales

  • Individual Work Packages to be defined by CERN

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Part 1 test validation1

Part 1 – Test & Validation

  • Deliverables for each phase are described in Chapter 5.1 of the Technical Specification

  • Failure to meet the stipulated deadlines for each phase shall imply

    • Financial penalty

      2% of phase estimate per week limited to 10%

    • Termination of the contract

      If maximum of 5 weeks is reached

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Part 2 on site installations

Part 2 – On-site installations

  • Work packages shall consist of typical new installations, or modification/dismantling of existing installations

  • Planning and scheduling shall be according to CERN users’ needs, please note that

    • Multiple work packages may be required simultaneously

    • No workload guarantee i.e., no work periods may exist

    • The Contractor shall adapt resources to manage these variations

  • After-Sales on-call service

    • For 2nd line interventions on systems no longer under guarantee

    • Intervention within 48h

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Work package execution

Work package execution

  • On-site visit

  • Request for Quotation

  • Technical & Financial offer

    • Based on DQE

  • Release Order

  • Scheduling

  • Supply & Installation

  • Acceptance Tests

  • Payment

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Acceptance control sheet

Acceptance Control Sheet

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Organisational issues

Organisational Issues

Local base

  • The contractor is expected to have a local base (§5.5.1 of TS)

    Mobile communications

  • All the field personnel of the contractor is expected to have mobile communication devices connected to the CERN Mobile network (§5.5.2 of TS)

    Storage areas and offices

  • No storage areas or offices shall be provided by CERN (§5.5.3 of TS)

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Working at cern

Working at CERN

CERN attaches particular care to provide a safe working environment,

  • See next presentation on “Environment, Health and Safety @ CERN” by J. Etheridge.

    Implications and time constraints

  • Radiation environment

    • Training, work medicine, dosimetry

    • Work restrictions and ALARA preparation

  • Access control & shutdown

  • Co-activities management and safety

  • RN84 and border crossing

  • Prevention Plan, PPSPS, VIC

  • First-aiders

    These issues are also addressed in the document “Working on the CERN Site” in Annex G of the TS

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Technical issues

Technical Issues

The Bidders’ attention is called to the fact that provided systems technical interfaces are particularly critical and shall be particularly scrutinised by CERN

Adequately skilled personnel shall be affected to the development & evolution of these interfaces

ADaMS

  • The provided systems shall interface with the CERN source of user data and access authorisation data called ADaMS (Access Distribution and Management System)

  • Detailed Description in §A.2.6 of the TS

    ORACLE Databases

  • The provided systems shall host their databases in the IT ORACLE infrastructure.

  • Detailed description in §A.2.7 of the TS

    IT technical network

  • The provided systems shall use the CERN TCP/IP Network (TN or GPN) and shall comply to the necessary computer security instructions given by the IT department

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Quoting

Quoting

General terms for each item in the DQE

  • Supply

  • Installation

  • Engineering

  • Documentation

  • Software Licences

    Applied in all items and complemented by specific provisions in Annex A

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Part 1 quoting

Part 1 - Quoting

  • Each phase shall be quoted individually

    • a Release Order shall be issued per Phase

    • The next phase shall be ordered after successful completion of the previous phase

  • Please note that for the Test & Validation platform

    • A separate and complete HW & SW infrastructure is required

    • A separate and complete Software Licence is required

  • Fill in ONLY the blue cells in the Tender Form Annex (DQE)

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Part 1 phase 4 quoting

Part 1 – Phase 4 – Quoting

  • Quote of the final production servers & licenses.

  • Please explicit the cost of fully integrating the external systems in your Access control system

    • As defined in the Annex A for each external system

    • If the system is already fully integrated explicit the relevant Item as zero cost and mention this in the “Reference” column

  • Each item can be object of a separate Release Order

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Part 2 quoting

Part 2 - Quoting

  • Fill in the blue-shaded cells only

    • Reference

    • Supply,

    • Installation,

    • Engineering & Integration,

    • Documentation,

    • SW Licence

  • Total Unit Price is calculated.

  • Manually fill in the Unit Price DAP (delivery included)

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Documents to be attached to the bid

Documents to be attached to the Bid

From Chapter 15 of the Tender Form:

  • DQE duly completed

  • A document indicating the time intended to allocate to the specific developments needed to interface your access control system with the CERN databases, as described in chapters A.2.5 and A.2.6 of annex A of the technical specification. Please provide the estimated number of hours and professional profile of the personnel that you intend to allocate to these developments,

  • An organisational chart indicating the organization structure and the personnel with their respective roles, responsibilities & qualifications,

  • General technical documentation including data sheets form the manufacturers on each of the proposed supply equipment (or respective web link from manufacturer).

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Errata

ERRATA

Correction of the Technical Specification

  • §A.3.7.1 Page 45 reads

  • a) INSIDE STiDLXS-W33AR/W door model

  • should read

    • a) INSIDE STiD LXS-W33BR/W door model

IT-3675/GS Bidders' Conference 3 Sep 2012 EDMS 1238534


Thank you for your attention

Thank you for your attention

Questions ?