An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Refit Close-outLean VSM ProjectTrident Refit Facility Kings Bay, GA Presenters: Refit Close-out Project Team September 08

  2. Team Debi Bemis Steve DeWitt Mike Hrivnak Ray LaFontaine Mike Litchfield Brett Mounsey • Danny Russell • Cynthia Rucker • Ernie Schwach • Christine Smith • Teresa Smith • Jill Winkelman

  3. Project Introduction OBJECTIVE Reduce variation and ambiguity in refit close-out processes to provide confidence in the accuracy of information and its sources 2008 GOALS ( show graph of future refits w/goals – progressing from end of project to May 09?) Goal for closing out projects in real time and in conjunction with the schedule – beginning in November, seasoned by May 09 Reduce the number of jobs not closed out at end of refit in LDS by _____% this year Reduce the number of jobs not closed out at end of refit in LDS by _____% by May 08 (or show graph of future refits w/goals – progressing from end of project to May 08?) VISION All paperwork is turned in and reconciled in real time according to job-specific schedule …thus upon boat departure/sea trials, all paperwork is turned in and reconciled. Create a method for objectively assessing and displaying refit status (green, yellow, red) at any point during the avail

  4. Significance Benefits of closing out refits in real time: Earlier planning of next refit, intelligent deferrals, elimination of replanning of numerous previously deferred jobs What happens when not closed out: Facility expands unnecessary time preparing What is involved in closing out a refit : Close out or defer AWR’s and CWP’s Close out WAF’s – in LDS Close out or defer ESR’s ASR- generated through LDS Official Refit Closeout Letter 4

  5. Current State Observations What is the requirement? Close within 7 days of departure - JFMM Average = 16 DAYS 5

  6. Closing Out a Refitwith respect to AWR’s and CWP’s Value Stream Map 6

  7. Variation in definition of work complete • Production • Test • Interferences installed after test • Sometimes sign if not complete – waiting on testing but need to close out refit Closing out AWR’s & CWP’s during a Standard Refit Current State VSMTRFKB 16 Sept 08 AWR’s AWR’s AWR’s AWR’s AWR’s Code 432 2% 30-40% corr maint, service routines, ALTS 60-70% PMR’s = Code 432 LWC Signs with Comments • Ship’s Force • LCPO’s • Div Officers • -3MC’s • Batch delivering AWR’s • from daily to once per refit • Refit Mgr, Ship Supt, Shop, PMA, Tank Coord – Mult roles check on status ARRS Review -CKI Signatures Final Action Taken (FAT) code Has job been issued Man hours Date Rework = appx. 20% ISIC (NSSC delegated to SUBMEPP) Batching AWR’s daily to once/refit Initiation to Action Response Time: 1d, 152m – 5w, 1d, 27m 5m– 1w 5 min 1 hr – 2 weeks 10 min 1 hr – 2 weeks 5 min 1 day 2 min 5 min

  8. Current State Observations What causes delays AWR’s not issued Parts or material on order Production ESR’s Growth Testing Waiting on QA Rework Waiting on installation of interference, paint or AWC Waiting on paperwork Lost paperwork CK not complete (ALTs) Hold jobs open to charge hours against it (can include time needed for clean up, de-staging and retooling) 8

  9. Current State Observations Refit in planning: Work completed during last refit but not closed out 740/44 (Total of 37 425 jobs rolled in to next refit) 22 jobs + 15 jobs comped by planners that we don’t know if they were done or not 742/38 (Total of 62 425 jobs rolled in to next refit) 20 jobs that have action taken coded plus 42 jobs comped last refit (1 from 2006) that have no action taken (don’t know if they are deferred….) 9

  10. Variation and Ambiguity in Processesobservations made through interviews with:General ForemenShop SuptsRefit MgrsShip Supts 10

  11. Current State Question: Reasons you don’t want to close out jobs when they are complete: (2) Want to use all their man hours (can include: sometimes need man hours for clean up, de-staging and retooling….)****** Still waiting on installation of interference, paint or AWC to finish. Parts/material still on order Boat work complete but shop still working Jill’s “pie in the sky question” - Can the shops keep unused hours or a percentage of unused hours as incentive to close out and use/learn actual times? Can we do this in the name of designating the hours as an aggregate “holding area” for finishing jobs (i.e. cleaning a valve after new one has been replaced) in the interest of load leveling? 11

  12. Current State Question: When do AWR’s go to the boat (for close out signature)? When supervisor signs off he gives it to GF and whenever GF delivers When ship sup delivers (2) When job is complete and LPO is there to witness – sign off on the spot Supt signs off and gives to GF who delivers daily to ship supt Gives to ship supt daily Saves until the end of the refit When complete work, shop supt take it to boat for Ship to verify completion of job then sign their block on the AWR Get them from shop in a pile, every day after 0900 meeting. If only have one, will wait until go down to the ship that day (930-1015). If boat chief is not there, then ship supt keeps AWR (Never give them AWR) Scenario: Looked at three AWR’s on a Ship Supt’s desk (representative scenario for most refits) Recommendations: (short term) LWC delivers LWC-signed AWR to Ship Supt by the following day’s production meeting; or the LWC gets signature from Ship’s Force upon completion of work then delivers to Ship Supt by the following day’s production meeting (mid term) Consider ship’s force signing their part on a list or database instead of individual forms assuming that TRFKB uses recommended definition of work complete. Consider alternative to meet requirement of Ship’s Force concurrence of TRFKB’s work complete (investigate SNAP/RMAIS correlation/exceptions). (long term) Make electronic and update in real time in a database 12

  13. Current State Question: How do you track jobs? PSR Intrusive - When AWC signs off the WAF, they know interferences are reinstalled Non-intrusive – direct communication and contact with the shops Final ship check by supervisor or work leader Supervisory job sight observation Performance of second checks with senior mechanics Stay abreast of job, go down and check, constantly call AWC Contact AWCs and/or Ships force if they don’t know if it is done (i.e. testing) Night sheets – physical board on the wall Daily observation of the job Recommendations: Designate PSR as official tracking mechanism for job status LWC’s update PSR status daily 13

  14. Current State How does paper get lost? If leave on the boat (ship sups) drop off. Former 3MC – said great time to sign AWR’s was at night. If chief grabs then goes and solves a different issue, then 3MC loses accountability. Ship sups put down in a shop, then forget Loss ______ What are the costs to not closing out jobs? Determine who has the expectations/accountability for job close out by due date (7 days after sail) and give visibility (Recommend: Refit Mgr) RO/PMA/Deputy PMA/Planning Officer/Business Manager/NSSC N4 - take action on poor performance within close out process Late reconciliation Late planning of new arrival Recommendation Standard process with roles and responsibilities (DH, PMA, SS, RM, _____410,____ - to _______ Include metrics in CO’s Brief 14

  15. ESR Process Observations: Pierside – can be managing 75-150 ESR’s in process at a time Number of ESR’s are increasing due to the age of the fleet and major avails Estimate 30 ESR’s in a standard refit Estimate 2000 ESR’s per year and increasing No link of ESR to AWR/JCN showing it is a liability 410 is jammed up at the end of a refit – getting departures turned around on a dime Responses: typically 1 day Work deferred may require a departure Issue an effective list every week on all ESR’s established for refit (briefed in or resulting from) Vision: Sign off ESR’s real time when work is complete Recommendation: Provide an automated link from ESR project file to 410/AWR’s Make effective 410 list a part of the process ESR work that needs to be deferred – put into correct refit LWC signs ESR in real time and turns in 15

  16. Future State Other recommendations: Ship Sup review of AWR should include review of comments i.e. “don’t allow work not complete” or “work deferred” to be in remarks when closing an AWR Per JFMM requirement ,NSSC take on current MDCO role of incoming to free up their capacity Refit Manager designated as primary POC for Refit Close-out Refit Manger Ship Supt be given close-out authority SUBMEPP review post close-out 16

  17. Thank you 17