1 / 12

In association with Chapter 16 Project Management: Networks and Finding the Critical Path

Learn how to perform a critical path analysis using the Activity on Node (AON) network method. Determine the earliest start, earliest finish, latest start, latest finish, and slack time for each activity. Identify the critical path, which is the longest path and the shortest time in which the project can be completed.

reedy
Download Presentation

In association with Chapter 16 Project Management: Networks and Finding the Critical Path

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. In association with Chapter 16Project Management:Networks and Finding the Critical Path Dr. Kimberly Dorsey

  2. The AON Network(AON=Activity on Node) Activity on Activity Node (AON) Meaning A comes before B, which comes before C. A C (a) B A A and B must both be completed before C can start. (b) C B B B and C cannot begin until A is completed. A (c) C

  3. A C B B D A C D A C B D The AON Network (cont’d) Activity on Activity Node (AON) Meaning C and D cannot begin until both A and B are completed. (d) C cannot begin until both A and B are completed; D cannot begin until B is completed. (e) B and C cannot begin until A is completed. D cannot begin until both B and C are completed. (f) Figure 3.5

  4. Determining the Project Schedule Perform a Critical Path Analysis • The critical path is the longest path through the network • The critical path is the shortest time in which the project can be completed • Any delay in critical path activities delays the entire project • Critical path activities have no slack time

  5. Earliest start (ES) = earliest time that an activity can start, assuming all the predecessors have been completed Earliest finish (EF) = earliest time that an activity can be finished Latest start (LS) = latest time that an activity can start without delaying the completion time of the entire project Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project Activity Description Time (weeks) A Build internal components 2 B Modify roof and floor 3 C Construct collection stack 2 D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test 2 Total Time (weeks) 25 Determining the Project Schedule Perform a Critical Path Analysis

  6. Activity Name or Symbol A Earliest Finish Earliest Start ES EF LS LF Latest Finish Latest Start 2 Activity Duration Determining the Project Schedule Activity Nodes Figure 3.9

  7. Forward Pass Begin at starting event and work forward Earliest Start (ES) Time Rule: • If an activity has only one immediate predecessor, its ES is the same as the EF of the predecessor • If an activity has multiple immediate predecessors, its ES is the highest of the the EF values of those predecessors ES = Highest EF of all immediate predecessors

  8. Forward Pass Begin at starting event and work forward Earliest Finish Time Rule: • The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) plus its activity time EF = ES + Activity time

  9. Backward Pass Begin with the last event and work backwards Latest Finish Time Rule: • The LF time for all ending activities is the same as the highest EF in the network • If an activity is an immediate predecessor for only one activity, its LF is the same as the LS of the activity that immediately follows it • If an activity is an immediate predecessor to more than one activity, its LF is the lowest of all LS values of the activities that immediately follow it LF = Lowest LS of all immediate following activities

  10. Backward Pass Begin with the last event and work backwards Latest Start Time Rule: • The latest start time (LS) of an activity is the difference of its latest finish time (LF) minus the activity time LS = LF – Activity time

  11. Computing Slack Time After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity • Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS – ES or Slack = LF – EF **Both of these will give you the same answer, OR SOMETHING IS WRONG in your forward or backward pass!**

  12. WHAT IS THE CRITICAL PATH? • Activities with zero slack are on the critical path. It: • Starts at the first critical activity in the project • Terminates at the last critical activity in the project • Includes only critical activities

More Related