An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. JRA1 in HADRONPHYSICS I3 Information on I3HP Negotiation Phase Contract into Force Start of Project Governance, Advance Payment, Reports JRA1 München

  2. I3HP Information • 29 activities: 12 JRA 7 + 1 Networking 9 Access • 48 contractors • 57 affiliated institutions • EU contribution 17 400 000 Euro JRA1 München

  3. Negotiation Phase • assure that project has necessary financial and human resources to carry out the proposed work • set up project time tables define sets of deliverables • material for final submission: • annex1 "Description of Work" and "Additional Financial Information" • Contract Preparation Forms JRA1 München

  4. Contract Preparation • Contract preparation forms (CPF's) verify legal and financial status of participants • Contract core contract and annex 1, 2 and 3 • Consortium agreement legal basis for relationship and responsibilities between contractors JRA1 München

  5. Contract into Force • Commission draws up contract, sends 2 copies to coordinator (happened 23 March) • coordinator signs and returns to Commission • Commission signs and returns one copy to coordinator; withdate of signature by Commission the contract enters into force ( 1st week April ) • coordinator sends copy to the contractors, together with form to accede (3x) • contractors sign and return to coordinator who signs and delivers to Commission and contractors JRA1 München

  6. Start of Project • contract enters into force with signature by Commission • the start of project is determined in the contract: for I3HP by negotiation this is 1. 1. 2004 • cost can be incurred on the project from the start date • since start date is prior to date of contract into force, future contractors take risk that contract might not be signed ( Æ no reimbursement) JRA1 München

  7. Governance • Coordinator of I3HP is INFN Frascati • 10 contractors are partners in JRA1 INFN, GSI, JLU-PIG, UHEI-PI, UMA, TUM, KFKI RMKI, JU, USL, UWNPD • representative of each contractor : Governing Board • spokesperson: Collaboration Committee JRA1 München

  8. Advance Payment • contribution is grant to the budget • payment to coordinator, who distributes to contractors • pre-payment (80%) for first period within 45 days after accession of last contractor • outstanding balance within 45 days following approval of reports JRA1 München

  9. Periodic Reports • cost reporting according to cost model (FC, FCF, AC) provided by each contarctor certification of cost (audit certificate) • activity report progress towards objectives and deliverables • reporting periods M1 – M12, M12 – M24, M24- M36 • special regulations for final report JRA1 München

  10. Cost Models • FC - Full Cost all eligible direct and indirect cost • FCF - Full Cost with indirect flat rate all eligible direct cost and a flat rate of 20 % for indirect cost • AC - Additional Cost with indirect flat rate all eligible direct additional cost and a flat rate of 20% of all direct additional cost JRA1 München

  11. Conclusion • expected date for contract into force is first week of April 2004 • start of contract defined to be 1. 1. 2004 I wish you successful work JRA1 München