An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Loraine Independent School District • Campus Improvements • Construction Update • July 22, 2013

  2. PROJECT STATUS

  3. FLOOR PLAN

  4. SCHEDULE

  5. SCHEDULE STATUS • Ceiling Grid and Ceiling Tile is Complete in K-12 • Paint is Finished Except touch-up in K-12 • Ceramic Tile is Complete. • Carpet and VCT is complete. • Standing Seam Roof at Cafeteria is Completion. • Millwork is Complete. • Mechanical and Electrical Systems are Complete in K-12 • Ag. Shop Remodel is Near Completion. • Pavement and Sidewalks are Near Completion

  6. Front Entrance

  7. Playground Canopy Frame

  8. High School / Junior High Corridor

  9. Cafetorium / Stage

  10. Gymnasium

  11. LOOKING AHEAD • Renovations of Ag. Building will be completed. • Pavement and Sidewalks will be completed. • Canopy will be completed. [Paint, Decking, Rails] • Gym Seating will be installed. • Final Clean Commences July 22 • Furniture Arrives on July 29 • LISD Staff Occupies New Building on August 5. • Staff Training on MEP Systems and Kitchen Equipment will be on August 15. First Meal in New Kitchen Aug. 26.