Loraine Independent School District. High School Athletics and Renovations Construction Update November 19 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Earthwork And Building Pad Prep Is Complete

adanna
Download Presentation

Loraine Independent School District

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Loraine Independent School District • High School Athletics and Renovations • Construction Update • November 19, 2012

  2. PROJECT STATUS

  3. PLANS

  4. PLANS

  5. SCHEDULE

  6. SCHEDULE STATUS • Earthwork And Building Pad Prep Is Complete • Underground Plumbing And Electrical Rough-in Is Complete In The Elementary Wing And Locker Room Areas • Underground Plumbing And Electrical Is In Progress In the Science Lab and High School Areas • Concrete Slab Has Been Poured At the Elementary Wing, And In Progress At the Gym and Locker Room Areas • Concrete Paving Is In Progress At The South Parking Area

  7. SCHEDULE STATUS • Storm Drainage Piping At West Side Of Building is 95% Complete • Tree Removal And Building Pad Preparation Is Complete At The Bus Barn Area • Additional Lots Owned By The District Have Been Cleared

  8. Parking Lot

  9. Plumbing Rough-in

  10. New Slab at Elementary Wing

  11. Restrooms at Elementary Wing

  12. LOOKING AHEAD • The First Concrete Paving Pour Will Be Completed This Week, And Continue Over The Next Month • The Locker Room And Partial Gym Area Slab Will Be Poured In The Next Two Weeks • Underground Plumbing And Electrical Rough-in Will Continue Over The Next Month • CMU At The Gymnasium And Locker Room Areas Will Begin In Mid December