Loraine Independent School District

Loraine Independent School District. Campus Improvements Construction Update December 17 , 2012. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Underground Plumbing And Electrical Rough-in Is Complete In All Areas

keegan
Download Presentation

Loraine Independent School District

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Loraine Independent School District • Campus Improvements • Construction Update • December 17, 2012

  2. PROJECT STATUS

  3. PLANS

  4. PLANS

  5. SCHEDULE

  6. SCHEDULE STATUS • Underground Plumbing And Electrical Rough-in Is Complete In All Areas • Concrete Slab Has Been Poured At The Elementary Wing, Gym, Locker Room And Junior High Classroom Areas And Is In Progress At The Science Labs, High School And Kitchen Areas • Concrete Paving Is Complete At The South Parking Area

  7. Completed Slabs: Junior High Classrooms and 1 Lab

  8. Completed Slabs: Looking NW at Jr. High Classrooms and 1 Lab

  9. Underground Rough-in: Looking East at HS Lab

  10. Parking lot

  11. LOOKING AHEAD • Masonry Is Scheduled To Begin December 17th • Steel Erection Is Scheduled To Begin The 2nd Week Of January • The Bus Barn Foundation Is Scheduled To Be Installed By Early January • The Kitchen, Administrative, Library And Computer Lab Areas Will Be Poured In The Next Month