City & County of San Francisco Capital Planning Program fy 2011-2020 DRAFT Capital Plan REVIEW Moscone Center Capital Improvements. February 22, 2010. Moscone Center North & South Capital Improvements: Overview.

pepper
Download Presentation

February 22, 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. City & County of San FranciscoCapital Planning Programfy 2011-2020 DRAFT Capital Plan REVIEWMoscone Center Capital Improvements February 22, 2010

  2. Moscone Center North & South Capital Improvements: Overview • Significant improvements to aging Moscone facilities are critical in order for the City to remain competitive in today’s convention and meeting marketplace. • Many first tier cities, like San Francisco, across the country are expanding and/or renovating their existing facilities, making them more attractive to planners. • The City is at risk of losing market share if major improvements are not initiated immediately.

  3. Moscone Center North & SouthCapital Improvements: Status • Airwall Replacements • Esplanade Ballroom – completed December 31, 2009 • Moscone North Hall E – completed February 15, 2010 • Fire Life Safety System Upgrade • 75% Complete • 120-day “Deep Dive” • Project Start – February 1, 2010 • Estimated Completion – May 27, 2010 • Comprehensive report of project scope, projected budget and timelines to be prepared by public/private partnership of DPW Project Management and Jones, Lang, LaSalle (JLL).

  4. Moscone Center North & SouthCapital Improvements: Project Budget • Proposed Expenditures: • COP Projects – $35,000,000 • TID Projects– $30,470,000 • Moscone Expansion Start Up Costs - $7,530,000 • Projected revenues • COP Proceeds – $35,000,000 (approximate net) • TID Proceeds – $38,000,000 (current projection) • Expenditures & Encumbrances to Date: • Esplanade Ballroom Airwall Replacement Project - $2,371,983 • Hall E Airwall Replacement Project – $1,238,895 • Fire Life Safety System Upgrade Project - $1,158,711 • Deep Dive – DPW $40,000 + JLL $224,450

  5. Moscone Center North & SouthCapital Improvements: Challenges/Opportunities • Difficult to schedule projects in a fully operating convention center • Capital improvements will result in infrastructure & aesthetic enhancements necessary for San Francisco to stay competitive

  6. Moscone Center Capital Improvements Questions?