290 likes | 531 Views
1/29. Transmission investment. Types of investment:maintenancecapacity increase (existing links)network expansion (new links). Introduction. Networkcosts. What if weare wrong?. Options. Conclusions. Currentincentives. . 2/29. Current situation. Transmission planning: CBA, based on load flow
E N D
2. 1/29 Transmission investment Types of investment:
maintenance
capacity increase (existing links)
network expansion (new links)
3. 2/29 Current situation Transmission planning: CBA, based on load flow forecasts.
Incentive based regulation (if applied) typically limited to operating & maintenance cost
popular method: network revenue growth rate = CPI-X+Q
the Netherlands exception: capital costs included
as a consequence major investments are made only if they are exempted from the revenue cap
4. 3/29 What do we want to achieve - goals Functions of transmission: transport, reliability & trade
Goal: economic efficiency, with respect to
maintenance
network availability (NTCs!)
congestion management
capacity increases
network expansion
Trade-offs between cost and quality
Second goal: integration of national markets, increasing competitiveness?
5. 4/29 Trade-off between cost and quality
6. 5/29 Objectives for network regulation Incentivise network users
efficient use of the network
optimal balance between cost and service
(in theory: marginal cost of service = marginal benefit)
Incentivise the TSO
optimal network management
find optimal balance between cost and service
regulation of monopoly rents
7. So… what are network costs?
8. 7/29 Categories of network investment In meshed AC networks
? parallel flows difficult to control
DC lines
flows are controllable
Linear/radial networks
no parallel flows
trade-off with generation easier to calculate
In last two cases: easier to determine the right incentives
? better prospects for IBR of TSOs
But most investment in meshed AC networks!
9. 8/29 Example: counter flows(all types of network)
10. 9/29 Counter flows Two transactions in opposite directions
? smaller load flow.
? More transactions can take place, but only if the counter flows really take place.
The network costs of a transaction can be negative!
When flows in a given direction double, energy losses quadruple ? cost increase not linear!
11. 10/29 Example: parallel flows
12. 11/29 An ill-planned new power line…
13. 12/29 Conclusion parallel flows The load flow is mainly determined by the impedance (resistance) of the lines, but constrained by their capacity.
Consequence: the load flow depends upon:
the location of generators
the location of loads and transformers to different networks
the resistance of the lines.
Electricity flows do not necessarily use the available capacity fully.
Load flow difficult to manage operationally.
? New network capacity must be coordinated with existing capacity.
14. Given these complications, what are current incentives?
15. 14/29 Incentives to network users: transmission pricing Ideal:
cost-based rates in case of no congestion
value-based rates in case of congestion
Two groups of transmission pricing methods:
Fixed, cost-based tariffs. Congestion handled separately. (Decentralized market design, typical for Europe)
Locational marginal pricing (nodal pricing).
(Integrated market design, typical of the USA.)
16. 15/29 The American way: nodal pricing A different price at every node in the network
You can only sell and buy electricity at the nearest node
The system/market operator varies nodal prices to reflect network capacity
congestion management is integrated in the process
overall prices are minimized, given demand, generation bids and network constraints
17. 16/29 Transmission pricing in Europe Fixed rates (typically not related to distance) allow market parties full freedom. TSOs intervene only when necessary to maintain balance or prevent congestion.
Problem: load flows unpredictable untill all trades have been closed and reported. Therefore costs are unpredictable.
tariffs are not efficient
18. 17/29 Current incentives to TSOs Build more capacity (especially interconnectors)
Reduce NTC on existing NTCs
In case of merchant interconnectors: reduce NTCs of other interconnectors to increase price difference.
? TSOs should not be in merchant projects! (like Britned)
19. 18/29 Links between incentives to TSO and network users The choice of transmission tariff, access rules, congestion management method affect the incentives to the TSO
The degree of unbundling affects the interests of the TSO
20. 19/29 But… incentives for what? How much capacity expansion in anticipation of demand growth?
Which network configuration is optimal?
When to build network capacity, when to rely on local generation investment?
What is an optimal cost level?
We don’t know what is optimal
21. So the incentives are probably wrong!
22. 21/29 Limits to incentives Further complication: lead time for investments ? risk of investment cycle
If we don’t know what is optimal, what are ‘good’ incentives?
23. 22/29 Asymmetry of social costs
24. 23/29 What if investment is not optimal? Asymmetry of welfare loss
transmission network costs in order of 1 €/MWh
VOLL in order of 1000 – 10 000 €/MWh
Given uncertainty, some overinvestment is prudent
(insurance against much higher cost of shortage).
25. What are the options?
26. 25/29 Options for providing incentives Benchmark competition
each transmission network is unique
Proxy incentives
for calculating NTCs
for reducing congestion
for estimating need for new capacity correctly
Possible solution to the issue of coordination with generation: ‘auctions’ for subsidies to G (Stoft)
FTRs?
27. 26/29 Opportunities for incentives to TSOs Regulation of TSO revenues ? efficiency
based on cost
based on benchmarks
Performance incentives
congestion
available network capacity
network reliability
economic performance of investments
typically proxy incentives
28. 27/29 Example of proxy incentives: NorNed Dutch & Norwegian TSOs
Regulated investment (rate base, not merchant)
Initial business case negative
TSO’s response:
capacity increase 600 MW ? 700 MW at no cost (!)
guarantees from neighboring TSOs for full utilization of cable
lower connection costs
Now business case neutral.
29. 28/29 Incentives in NorNed Dutch regulator attached conditions to regulatory approval: incentives relating to
moment that cable is operational
under/over budget realisation
availability of cable
30. 29/29 Conclusion Options for incentive-based regulation limited
better in simple, linear networks and for DC links
when theoretically optimal incentives are not feasible, proxy incentives may be a solution
evolution of pragmatic regulations ? credibility problem, also repeat games between sector and regulator (Joskow)
The social cost of too little investment is much higher than the cost of some excess investment.
Given the complexity: better safe than sorry
simple regulation, slight overinvestment might be the most secure solution.