1 / 30

LHC Electronics irradiation tests in the CNGS side gallery September 2009 – partial results

LHC Electronics irradiation tests in the CNGS side gallery September 2009 – partial results. D.Kramer for the RADWG.

malana
Download Presentation

LHC Electronics irradiation tests in the CNGS side gallery September 2009 – partial results

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LHC Electronics irradiation tests in the CNGS side gallerySeptember 2009 – partial results D.Kramer for the RADWG Thanks to B.Todd, E.Gousiou, E.Calvo, E.Effinger, R.Denz, K.Roeed, J.Lendaro, D.McFarlane, M.Brugger, EN/MEF, DG/SCR, Fluka team and the RadMon team (T.Wijnands, A.Nyul, C.Pignard) report to LMC

  2. Outline • Test facility overview • Planning of slots • Calibration of test positions • User results • CRYO • BIC/PIC • BLM • BPM • QPS • HTS CL to be presented next time • WorldFip to be presented next time • TE/EPC no data yet • SURVEY no data yet report to LMC

  3. Testing area in the TSG4 side gallery of CNGS Radiation fields similar to the ones expected in LHC Area available after the displacement of the CNGS electronics to the ventilation chamber report to LMC

  4. 2 Test areas – High & Low flux and dose rate with multiple calibrated locations Hottest test area in TSG46: ~ 1.5 Gy(SiO2)/week ~ 2.6 1010(1MeV n eq.)cm-2/week HTS CL heaters Target chamber QPS New FLUKA simulations are now available thanks to K.Roeed Survey WorldFip Target chamber RadMon BIC/PIC Hottest test area in TSG45 : ~ 12Gy(SiO2)/week ~ 2.8 1011(1MeV n eq.)cm-2/week This is expected in the LHC arcs* or UJ56/14/16 in 1 nominal year (10Gy/y, 3e11cm-2) BLM CRYO TE/EPC *Alongside a dipole report to LMC

  5. Calibrated radiation field data for all test locations accessible via dedicated Java GUI Hottest test area TSG46: ~ 1.5 Gy(SiO2)/week ~ 2.6 1010(1MeV n eq.)cm-2/week Hottest test area TSG45 : ~ 12Gy(SiO2)/week ~ 2.8 1011(1MeV n eq.)cm-2/week report to LMC

  6. Calibrated radiation field data for all test locations accessible via dedicated Java GUI Hottest test area TSG46: ~ 1.5 Gy(SiO2)/week ~ 2.6 1010(1MeV n eq.)cm-2/week Like it is the case for FLUKA, Safety Factor of 2 should be used for all the CNGS measurements (high gradients, small detector size) Example for the BLM location – 1month time By assuming all the devices to be installed in the worstlocations, the estimations are more conservative than 2 times (for SEE related failures) Hottest test area TSG45 : ~ 12Gy(SiO2)/week ~ 2.8 1011(1MeV n eq.)cm-2/week report to LMC

  7. Planning for the user tests Temporary procedure for handling irradiated electronics was put in place for CNGS. Valid until 30/11/09. Radioactive electronics WORKSHOP has to be used afterwards. • Additional measurements: • Activation of water samples • TLD (Li6 & Li7) • Au & Bi activation foils • BLMI sensitivity to thermal neutrons • All users requesting beam time in 2009 received a slot • Only the vacuum group didn’t receive the turbo pumps -> no tests possible report to LMC

  8. USER test results • The presented radiation levels are for nominal LHC beam • Estimations for the 2009/10 operation are added when necessary • CRYO • BIC/PIC • BLM • BPM • QPS • HTS CL not enough data • WorldFip not enough data • TE/EPC no data yet • SURVEY no data yet report to LMC

  9. Tunnel Electronics CRYO • Tunnel electronics (~9500 channels in LHC tunnel) have received till now a cumulated dose of: ..and the tests are still ongoing. • No Single Event Errors • Output accuracy still within specs • ( <0.3% ) • Resistance measurements of 5 conditioners: • Temperature reading (18 Channels) • Helium level reading (12 Channels) • Digital inputs (24 Channels) • Cold mass electrical heater DC supply (4 Channels) • FIP communication (8 agents) • Power supply (2 cards) Tunnel equipment in CNGS: 120 0 report to LMC 51 Resistance (Ω) 48 TID (Gy)

  10. Protected Areas ElectronicsCumulative Effects Failures CRYO Safety factor 2x to be applied • QRL electrical Heater AC supply • (~45 channels in protected areas): • Failing component: solid state relay. • Planning of moving electronics or • shielding of protected areas. • Insulated Temperature reading (~2400 channels in protected areas): • Failing component: DC-DC converter. • Planning of scheduled replacements. • Same results for several channels and reproduced in two different CNGS locations. report to LMC

  11. Protected Areas ElectronicsSingle Event Upsets CRYO • Insulated Temperature Conditioners (~2400 channels in protected areas): • Failing component: ISO 150 Digital Isolator. • Mitigation technique for LHC (in progress): soft resetautomatically forced by the control system; • No influence on proper operation of the machine. • Same results for 12 channels and reproduced in two different CNGS locations. report to LMC

  12. USER test results • CRYO • BIC/PIC • QPS • BLM • BPM report to LMC

  13. CPLDs Used in the Interlock Systems Beam Interlock System (5V) 500nm XC95288 x 300 UA, UJ, RR XC95288XL x 34 (3.3V) 350nm UA, SR, TZ Power Interlock Controllers (5V) 500nm XC95144 x 36 UA, UJ, RR 95288/144 (5V) failure = maintenance required = not machine critical 95288XL (3.3V)failure = can compromise safety* N.B. Whole BIS is redundant = *needs two identical failures during a mission 95288XLis used in the control VME chassis TE/MPE/MI has installed a Radiation Test Bench in CNGS XC95144 x 32 XC95288XL x 32 Almost = # in LHC report to LMC

  14. XILINX CPLD test setup in CNGS for BIS and PIC • Dedicated test setup produced only for the radiation tests • One test card (5V) failed after 77Gy • Setup remains in CNGS to verify total dose resistance of the CPLDs • No destructive Latchup observed so far (to be confirmed) report to LMC

  15. XC9500XL (3.3V)[ UAs, SR, TZ76 etc ] • Failure (SEE induced) cross-section per device = • 2.8e-10 cm2 • In UA87 one expects high energy hadron fluence less than (conservative!) • 1e8 cm-2/y • The resulting failure rate for 1 device = 0.025 SEEs/y • If all the 36 CPLDs were in UA87 (not considering the shielding installed last week), we would get • 0.9 failures/y, out of which • 20% produce loss of redundancy (5.5y MTBF) • 80% lead to a false dump (1.4y MTBF) • We have to keep in mind that this is a low voltage device and might be sensitive to thermal neutrons. In areas like UAs their fluence could be up to 10xhigher than hadrons>20MeV (Fluka analysis to be performed). • If this is true, the 0.9 failures/y is a conservative but not exaggerated estimation. • Tests in thermal neutron beam are being considered report to LMC

  16. XC9500 (5V) • The device has a very low error cross-section! • Failure (SEE) cross-section  = • 3.8e-13 cm2 • We can assume conservatively • 1e9cm-2/y for the high energy hadron fluence in the RRs. • We get then 3.8e-4 SEEs/y/device which makes • 0.14 SEEs/y for the 366 devices, i.e. 7.2y MTBF • In 10% of cases the SEE produces a False dump • In 90% of cases the SEE produces a Monitoring problem • These figures are of the same order of magnitude as the Electrical Reliability of the devices (according to Xilinx) • In both cases above we don’t care about the total dose, one should not reach 1Gy/y for the concerned locations (except the locations below) • Relocation from UJ56/UJ14/16 is in preparation (cables placed, new location identified) report to LMC

  17. USER test results • CRYO • BIC/PIC • QPS • BLM • BPM report to LMC

  18. Quick report on the early QPS measurements – WorldFip problems • Field-bus coupler type DQAMGS (new QPS layer) • Errors produced by SEUs in the WorldFip part • Using latest MicroFipTM and FIELDRIVETM (line driver) version • Data are still readable but no longer updated -> *Access required prior to next fill • Cross section ~ 2.8x10-10cm2 • Assuming 4x1010cm-2/y (10Gy/y) in the arcs and 450 devices one gets: • 14 errors*/day • Hardware solution was found and being successfully (so far) tested in CNGS • Accelerated SW compatible MicroFipTM and FIELDRIVETM development would be much appreciated not only by the QPS team for any future developments • This year’s tests in CGNS confirmed the radiation tolerance of the detection systems of the new QPS layer including the power supplies. Detailed evaluation still to be done. report to LMC

  19. USER test results • CRYO • BIC/PIC • QPS • BLM • BPM report to LMC

  20. BLM- System: Installation overview • Arc – Installation • In all the arcs from 12L – 33L, 12R – 34R • Expected Radiation levels: worst case Dose = 1-10 Gy/y (1MeV eq. neutrons = 3*1010-3*1011 cm-2/y) • 360 * BLECF Card (Analogue data acquisition cards) • 360 * Hand made power supplies • Straight Section Installation • RR13, RR17, UA23, UA27, UJ33, UA43, UA47, RR53, RR57, UJ63, UJ67, RR73, RR77, UA83, UA87 • Expected Radiation levels: worst case Dose = <0.7Gy/y (1MeV eq. neutrons = 1*109-1*1010cm-2/y) • 309 * BLECF Card (Analogue data acquisition cards) • 74 * 5V Power supplies (Haltec-USR515-5A, of-the-shelf) • 37 * 2.5V Power supplies (Haltec-USR515S-2A, of-the-shelf) report to LMC

  21. BLM- System: test conclusions • Power supplies 5V: • 19 years of nominal LHC operation possible • Power supplies 2.5V: • 20 years of nominal LHC operation possible • BLECF (Tunnel acquisition card): • more than 20 years LHC operation possible • 1 SEE induced failure (false dump) observed • Cross section = 2.2x10-13cm2, this means for 600 cards assuming all in the arcs • 70 days MTBF (fail safe)

  22. USER test results • CRYO • BIC/PIC • QPS • BLM • BPM report to LMC

  23. BPM electronics Tested up to 123 Gy (>10 nominal years) Chassis similar to the one installed in LHC. • 1 Power supply • 1 uFIP controller card OK • 330x in LHC • 1 uFIP controller card • 1 Intensity card • 2 WBTNs OK failed SEEs • 2160x in LHC • 330x in LHC • 330x in LHC Eva Calvo (BI/QP)

  24. BPM electronics Tested up to 123 Gy (>10 nominal years) • Intensity card failed very soon • Aim of the intensity cards is to detect obstacles in the machine during its initial operation (low intensity beam) • 3x1010 cm-2 (1MeV n. eq.) means ~ 0.5 nominal LHC years • Most probably not an issue for 2009/10 • Measurement corrupted after the event (SEL?, card to be inspected) • uFip controller card sensitive to SEEs • sending the sensitivity settings of the WBTNs, launch calibrations, or monitoring the power supplies • Return to the default state after SEE (calib. off, high sens.) • SEE Cross section = 4x10-12cm2thus2.2days MTBF • Worst case: 250um offset for 60s for 1 channel – can be compensated by orbit feedback -> not an issue for operation report to LMC

  25. Summary (detailed report to be written after the end of tests) • CRYO tunnel cards perform very well – no concerns • Some CRYO non-tunnel cards sensitive to total dose, replacements after 0.5y of nominal beam in UJ14/16/56 – not critical for operation • Some CRYO non-tunnel cards sensitive to SEUs, software mitigation in progress (6 SEUs/h for nominal beam) • BIC VME chassis uses sensitive CPLDs but only a small number and not in the most critical areas (5.5y MTBF) – verylittle concern • BIC/PIC installations use low cross-section CPLDs which always fail in a safe way (7.2y MTBF) – no concerns

  26. Summary (detailed report to be written after the end of tests) • No cumulative effect problems expected for the BLM system • Marginal sensitivity of tunnel card to SEE means 70 days MTBF (fail safe, handled by remote reset) • Very sensitive latest WorldFip chip could compromise the new QPS layer – hardware solution looks very promising (450 cards in LHC) • If uncorrected, 14 errors/day in nominal conditions (no issue for safety) • BPM cards showed no radiation related problems, intensity cards don’t stand high intensity (needed for low intensity), uFip card sensitive to SEEs (2.2days MTBF) but handled by the orbit feedback • CNGS side gallery proved to be a very useful facility !! • Measurements are still ONGOING

  27. Summary – failure rates expected for 2009/10* operation *40 times lower losses assumed in the arcs in 2009/10 compared to nominal ( very CONSERVATIVE )

  28. Reserve slides – CNGS Fluka simulations report to LMC

  29. Simulated radiation fields of the selected most critical non-tunnel locations *Assuming 2 shots per week on TED report to LMC

  30. BLM- System: Status CNGS Result power supplies PS1, PS2, PS3 and BLECF RadMon data for the BLM crate positioned in TSG45. Beam intensity data was scaled with the calibration data from 2009.

More Related