BETTER PREPARED PROJECTS The Quality and Incompleteness of Design Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend, OregonUnited States August 12-14, 2010
Better Prepared Projects CONTENTS • Problematic of Projects • 2. ProposalsforSolutions 2
Better Prepared Projects 1. Problematic of Projects TheMexicanLaw of Public Works and Related Services establishesthefollowing: “To carryoutanypublic work, itisrequiredthatthestudies and projects, constructionspecifications, qualitynorms and thebuildingprogram are fullycompleted”. 3
Better Prepared Projects 1. Problematic in Projects However: In reality, on many occassions, public work bids are offered without Master Projects being complete which guarantee the correct execution of the project. 4
Better Prepared Projects 1. Problematic in Projects This situation provokes a series of adverse elements that affect the time and cost in finishing these works. Among them: ● Authorization of additional resources to obtain the neccessary elements for completion of the project. ● Changes and modifications in the building process of the works, with consequent imbalances in the contracts and cost increases. ● Differences and / or controversies bewteeen the parties , that may provoke nonconformity and litigation. ● The calendar for release of resource allotment is not done on time. ● Start projects in the third quarter of the year. ● Cancellation of resources by the Secretariat of Public Finance and Credit. 5
Better Prepared Projects 1. Problematic in Projects Deficiency: Currently no mechanism exists to assure that reserves for Master Projects are set aside to guarantee the correct implementation of the public work. 6
Better Prepared Projects 2. ProposalsforSolutions Giventhepresentsitutation CMIC ispromotingtwoproposalsforthegeneration of reserves forMasterProjectsthrough: ● The 32 Stategovernments (proposal 1) ● The Federal Government (proposal 2) 7
Better Prepared Projects 2. ProposalsforSolutions Proposal I: “National Reserves for Master Infrastructure Projects ” with State Governments 1 2 3 4 5 6 Bids for public works Include an obligation of retaining 5 per thousand State governments Decentralized Organisms or with state participation Economic Proposal The 5 per thousand is specified in a unit price analyisis Estimate of public work Adjudication of contracts Construction execution 9 10 11 7 8 Public trusts in different regions of the country (center, south, northeast, northwest) Financing and operation with reserve for infrastructure Retención de 2 al millar para capacitación Retention of 5 per thousand/direct cost Licitaciones de obra pública 8
Better Prepared Projects 2. ProposalforSolutions Proposal II: “National Reserves for Master Infrastructure Projects” with the Federal Government 2 3 1 4 Assigned budget for investment in federal government entities and institutions. Execution of public works Legislative power Secretariat of Finance and Public Credit To exercise 5 at 7% 9
BETTER PREPARED PROJECTS The Quality and Incompleteness of Design Documents CMIC Presentation to the North American Construction Federation Conference Sun River Resort- Bend, OregonUnited States August 12-14, 2010