An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fermilab Test Beam Facility Aria Soha All Experimenter’s Meeting September 16, 2013

  2. Summary http://www-ppd.fnal.gov/FTBF/

  3. Infrastructure • MWPC stations, New Read-out – Working! • Thanks Sten & Terry! • Motion Tables (2B, 2C, 1A) – • New stepping motors • Now controlled through ACNET • Calibrated (w/help from AD Controls) • Silicon Telescope • Strip Telescope still in the works, • Pixel Telescope installed (out of beam) http://www-ppd.fnal.gov/FTBF/

  4. Infrastructure Work continues on: • HRT Area (M03) • Table design being finalized, ordering parts • MCenter Control Room • Walls (T&M work expected to start in Sept) • HVAC • Shielding Ready to go http://www-ppd.fnal.gov/FTBF/

  5. Schedule • Sept 4 – Oct 9: Intensity limitation due to F4 berm work • Oct 2 – Nov 5: MCenter work, roof work, (Berm work cont.) http://www-ppd.fnal.gov/FTBF/schedule • Now with Make-up Time • Booked until July 2014 • T-1038 (First Exp) installed Sept 4, ORC on Sept 6 (next slide) • T-992, T-1047T-1043, T-1045, install Wednesday morning ORC expected. (2 weeks) • T-1031 begin installing Wed in M03 http://www-ppd.fnal.gov/FTBF/

  6. T-1038 • lb-W crystals w/APD’s on front (collect reflected light) studying the effect of MIP’s through APD’s • Took Pions @ 16 GeV (Thank You!) • Collecting MIP’s right now (just collecting statistics don’t care about spill quality or consistency) • Saw electron Showers (beam 30% e-) • Next: e- beam with W target in front of detector to get more MIP’s through APD’s • 1/8 of this detector will be installed in the PHENIX detector in November http://www-ppd.fnal.gov/FTBF/

  7. TSW’s In Progress http://www-ppd.fnal.gov/FTBF/TSW http://www-ppd.fnal.gov/FTBF/

  8. Summary http://www-ppd.fnal.gov/FTBF/