1 / 21

Lower Rio Grande Valley (LRGV) Import

Lower Rio Grande Valley (LRGV) Import. Lower Rio Grande Valley interface. Valley Interface 1. North Edinburg - Lon Hill 345 kV 2. Ajo – Rio Hondo 345 kV 3. Raymond 2 – MV Yutt 138 kV 4. North Edinburg - Rachal 138 kV 5. Roma Switch – Falcon Switch 138 kV. RPG Meeting.

lavi
Download Presentation

Lower Rio Grande Valley (LRGV) Import

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lower Rio Grande Valley (LRGV) Import RPG Meeting

  2. Lower Rio Grande Valley interface • Valley Interface • 1. North Edinburg - Lon Hill 345 kV • 2. Ajo – Rio Hondo 345 kV • 3. Raymond 2 – MV Yutt 138 kV • 4. North Edinburg - Rachal 138 kV • 5. Roma Switch – Falcon Switch 138 kV RPG Meeting

  3. Existing LRGV System • The AEP-TCC, Sharyland Utilities, Magic Valley Electric Cooperative (MVEC) and Public Utilities Board of Brownsville (PUB) transmission system currently serve approximately 2,200 MW of summer peak demand in the LRGV area. • There are three combined-cycle generating stations in the LRGV with a combined capability of 1,592 MW. • Additionally PUB has 4 units totaling approximately 120 MW on the eastern side of the LRGV. RPG Meeting

  4. LRGV System Load Growth • The McAllen-Edinburg-Mission and Brownsville-Harlingen-San Benito areas are has grown significantly in the past few years (15 year average annual MW growth, based on the summer peaks is ~ 63 MW* or ~ 4.3%*). • Extremely cold weather can result in a winter peak demand to significantly exceed the forecast and the summer peak levels. • Extreme cold weather on February 3, 2011 has set an all-time new record peak of approximately 2,734 MW. • Historical data (by AEP) indicates that in the past 15 years the winter peak demand has exceeded the summer peak four times (1997, 2007, 2010 & 2011) • * excluding PUB area RPG Meeting

  5. Actual Summer and Winter Peak for LRGV for past 15 years RPG Meeting

  6. Actual Summer and Winter Peak for LRGV since 2007 RPG Meeting

  7. LRGV Winter Peak & Temperature correlation RPG Meeting

  8. Summer Peak & Temperature correlation RPG Meeting

  9. SSWG Planning Case - LRGV Area Summary RPG Meeting

  10. LRGV Power Flow Analysis • The power flow analysis indicates the limiting contingency is the loss of a 345 kV transmission line, with the largest LRGV generation station out of service (all units @ combined cycle facility). • The above NERC category C contingency falls with in the ERCOT planning criteria section 5.1.4 “In the case of a Combined Cycle Facility, a “single generating unit” experiencing a forced outage shall be defined as the entire train unless the combustion turbine and the steam turbine can operate separately”. • Based on the 5YTP models the worst contingency results in the overload of the remaining 345 kV transmission line in 2014 summer peak condition at load level of 2,426 MW. RPG Meeting

  11. 2015 Summer Peak Power Flow : Base Case RPG Meeting

  12. 2015 Summer Peak Power Flow : Generating Station out of service + 345 kV line RPG Meeting

  13. LRGV Voltage stability Analysis • The voltage stability analysis indicates that the NERC Category C contingency limits the import capability to the LRGV. • Based on the 5YTP model, the voltage stability limit for the LRGV is approximately 2,560 MW. • The actual steady state voltage limits could be lower than the voltage stability limit. RPG Meeting

  14. 2011 Summer Peak Voltage Stability RPG Meeting

  15. LRGV Thermal/Voltage stability Summary • The thermal limits based on the current ERCOT SSWG planning model/criteria will exceed by 2014. • The voltage stability only exceed the thermal limits by approximately 150 MW. • The voltage stability limits being so close to the thermal limits indicate that increasing the thermal capacity of the existing LRGV interface would not significantly improve the load serving capacity. • There is a need for transmission or market solution in the LRGV to meet the forecasted load beyond 2014. RPG Meeting

  16. Operational issues affecting the LRGV • A major operational issue is the difficulty to grant clearances for both transmission and generation maintenance outage in the LRGV. • There is a limited time windows to grant maintenance outages in the LRGV and any extreme weather during this period could require load shed. • There is a potential for severe weather (hurricanes) that could affect both the existing 345 kV lines sourced from the Corpus Christi area and significantly reduce the load serving capability in the LRGV. RPG Meeting

  17. Historical AEP-TCC Valley Load Data • Historical AEP-TCC Valley load data presented in the next few slides provide show some evidence of peak windows. • Based on the McAllen, Texas weather station data back to1960. RPG Meeting

  18. Historical AEP-TCC Valley Load RPG Meeting

  19. Historical AEP-TCC Valley Load RPG Meeting

  20. Historical AEP-TCC Valley Load McAllen, TX Annual Minimum Daily Average Temperature (1960 to Present) 50 45 40 35 30 25 Only 6 times in the last 51 years has 20 McAllen's annual minimum daily average temperature been 32 or 15 below. It is the first time since 1997. 10 5 0 1961 1963 1965 1967 1969 1971 1973 1975 1977 1979 1981 1983 1985 1987 1989 1991 1993 1995 1997 1999 2001 2003 2005 2007 2009 2011 RPG Meeting

  21. Questions? March 12, 2010 RPG Meeting

More Related