Peningkatan Pengendalian Proses Bisnis untuk Mencapai World Class Services

Peningkatan Pengendalian Proses Bisnis untuk Mencapai World Class Services. RAPAT KOORDINASI TRIWULAN IV-2013 PT. PLN (PERSERO) PEMBANGKITAN SUMBAGSEL BIDANG PRODUKSI. Bandar lampung 8-10 januari 2014. PREDIKSI REALISASI KINERJA 2013. EFOR 2013 >> MASALAH Target 1,8 | Realisasi 4,55.

Download Presentation

Peningkatan Pengendalian Proses Bisnis untuk Mencapai World Class Services

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Peningkatan Pengendalian Proses Bisnisuntuk Mencapai World Class Services RAPAT KOORDINASI TRIWULAN IV-2013PT. PLN (PERSERO) PEMBANGKITAN SUMBAGSELBIDANG PRODUKSI Bandar lampung 8-10 januari 2014

  2. PREDIKSI REALISASI KINERJA 2013

  3. EFOR 2013 >> MASALAH Target 1,8 | Realisasi 4,55

  4. SDOF 2013 >> MASALAH Target 1,5 | Realisasi 1,79 Target SdOF : 1,5 Realisasi SdOF : 1,79 Jumlah unit : 82 unit Equivalent jumlah kali trip : 123 kali Realisasi jumlah kali trip : 147 kali

  5. 2013 – Penyerapan Gas Catatan : Gangguan PLTG Keramasan 2 sejak Februari 2013 telah menurunkan penyerapan gas sebesar 4 BBTUD Gangguan PLTG AKE sejak Agustus 2013 telah menurunkan kemampuserapan gas s.d. 34 BBTUD di PL Keramasan

  6. 2014 – Penyerapan Gas

  7. Gas Make Up Borang GMU s.d. November 2013 5.246.929 MMBTU

  8. Gas Make Up Keramasan GMU s.d. November 2013 2.454.271 MMBTU

  9. 2013 – Efisiensi Working Capital Data sementara, masih menunggu hasil rekon keuangan dan update SAP Tambahan material belumterpakai : 32M; coil bar; PLTU Ombilin 31M; mandatory part; PLTP Ulubelu 13M; TIV; PLTA Maninjau 11M; turbine rotor; PLTU Bukit Asam

  10. REKAPITULASI RENCANA dan REALISASIOUTAGE MANAGEMENT 2013

  11. GRAFIK RENCANA dan REALISASI OUTAGE MANAGEMENT 2013 TOTAL RENCANA = 43 TOTAL REALISASI = 26 60,47 %

  12. REKAPITULASI OUTAGE MANAGEMENT 2013

  13. TOTAL RENCANA = 43 GRAFIK RENCANA dan REALISASI OUTAGE MANAGEMENT 2013 TOTAL REALISASI = 26 60,47 %

  14. Rencana Pemeliharaan Periodik 2014

  15. PEMBANGKIT YANG MENGALAMI PERPANJANGAN DURASI PELAKSANAAN OVERHAUL • 1. SEKTOR KERAMASAN : • PLTG TALANG DUKU, PEKERJAAN MAJOR INSPECTION (MI), RENCANA DURASI 45 HARI, REALISASI 163 HARI KETERLAMBATAN SELAMA 118 HARI, KARENA ADA PERBAIKAN SECOND STAGE NOZZLE dan GANGGUAN SISTIM CONTROL. • 2. SEKTOR OMBILIN : • PLTG PAUHLIMO # 3, PEKERJAAN HOT GAS PATH INSPECTION (HGPI) RENCANA DURASI 35 HARI, REALISASI 74 HARI KETERLAMBATAN 39 HARI, KARENA ADANYA PEKERJAAN REBABIT BEARING TURBIN.

  16. MONITORING PELAPORAN OUTAGE MANAGEMENT 2013

  17. PERINGKAT PROPER TTAHUN 2013BERDASARKAN UU 32 TAHUN 2009 E M A S SOMB (PL PAUH LIMO & OMBILIN) H I J A U PL INDRALAYA-SKRM B I R U STAR,SBAM, SKRM (PL KERAMASAN) MERAH

  18. REALISASI PENYERAPAN ANGGARAN 2013 (dalam ribuan Rp)

  19. Kapasitas Terpasang dan Jumlah Pegawai

  20. Rasio Pegawai per Pembangkit Rasio (MW/Peg) Kapasitas (MW) Total Rasio Pegawai KITSBS 1,83 MW/Pegawai

  21. Rasio Pegawai per Sektor Rasio (MW/Peg) Kapasitas (MW) Total Rasio Pegawai KITSBS 1,83 MW/Pegawai

  22. Peningkatan Pengendalian Proses Bisnis untuk Mencapai World Class Services ... Next Step ! 4,8 MW/Peg. Otomatisasi sistem operasi Penambahan unit kapasitas besar Restrukturisasi organisasi Alih daya pekerjaan Integrasi administrasi Job enrichment Peningkatan kapabilitas SDM 1,83 MW/Peg.

  23. TerimaKasih

  24. Suplemen3Tambahan Kapasitas 2014 PLTU Teluk Sirih 1 - 2 2 x 112 MW (Jan & Apr-14) PLTG Sewa Pyslcah 30 MW (Feb-14) 50 MW (Jun-14) PLTGU Keramasan 2 x 40 MW (Jan-14) PLTG Sewa Krmsan 50 MW (Jul-14) PLTU Tarahan 5 - 6 2 x 100 MW (???) total tambahan sebesar 634 MW

  25. Suplemen 4Pasokan Gas Jambi BBTUD Pemasok Waktu 18 EHK Pusat Listrik : Payo Selincah MW Pemasok 6 x 5.2 PLTD Payo Selincah 2 x 30 PLTG Batanghari 1 & 2 5 18 PLTG Batanghari 3 BBTUD Pemasok Waktu MRS Simp. Bayat MRS Tempino 18 2 x 50 PLTG BOT Eramas 25 PTJM 9-Feb-2019 pipa TGI Grissik - Duri GRISSIK (Cophi) 2 DURI 5 EMP Gelam 14-Mei-2017 2 UBEP Pusat Listrik : Sei Gelam MW Pemasok 90 PLTMG Sei Gelam 12 PLTMG Kerta Bumi Teknindo 25

  26. Suplemen 5Pasokan Gas Keramasan BBTUD BBTUD BBTUD Pemasok Pemasok Pemasok Waktu Waktu Waktu 3 17 18.3 PDPDE Medco Medco Okt 2021 April 2015 Nov 2014 5 14 8 Pusat Listrik : Keramasan Pusat Listrik : Talang DUku Pusat Listrik : Merah Mata Pusat Listrik : Indralaya MW MW MW MW Pembangkit Pembangkit Pembangkit Pembangkit 12 15 2 x 40 45 GT 1.1 Indralaya PLTG Borang 1 PLTGU Keramasan PLTG Talang Duku 1 35 2 x 15 2 x 30 38 GT 1.2 Indralaya PLTG Talang Duku 2 PLTG Borang 2 & 3 PLTG Keramasan 3,4 21 2 x 10 40 30 PLTG Keramasan 1,2 PLTMG Sewa Borang PLTG Talang Duku 3 ST 1.0 Indralaya BBTUD BBTUD Pemasok Pemasok Waktu Waktu 8 15 Pertamina PGN Nov 2015 Juni 2019 15 5 14 Medco Interruptible Juni 2014 Okt 2014 Pusat Listrik : Jakabaring MW Pemasok 3 x 18 PLTG Jakabaring 1,2,3 dari Pertagas 17 18.3 3

  27. Suplemen 6PolaOperasi PLTG TalangDuku PLTG #3 PLTG #3 PLTG #2 PLTG #2 PLTG #1 Pola operasi awal (gas : 8 BBTUD) Pola operasi dengan gas interruptible (gas : 13.8 BBTUD) 1 Des 2013 – 30 Juni 2014