Briefing on Oak Ridge National Laboratory’s Automatic Shutdown and Remote Control Valve Study

Briefing on Oak Ridge National Laboratory’s Automatic Shutdown and Remote Control Valve Study. Patrick Landon, P.E. Engineer - Office of Pipeline Safety 202-366-3814 patrick.landon@dot.gov. Liquid and Gas Pipeline Advisory Committees December 11 and 13, 2012.

halona
Download Presentation

Briefing on Oak Ridge National Laboratory’s Automatic Shutdown and Remote Control Valve Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Briefing on Oak Ridge National Laboratory’s Automatic Shutdown and Remote Control Valve Study Patrick Landon, P.E. Engineer - Office of Pipeline Safety 202-366-3814 patrick.landon@dot.gov Liquid and Gas Pipeline Advisory Committees December 11 and 13, 2012

  2. Established in 1943 as an integral part of the Manhattan Project Department of Energy's largest science and energy laboratory Managed by a limited liability partnership between the University of Tennessee and Battelle Memorial Institute known as UT-Battelle ORNL operates nine user facilities that draw thousands of research scientists and visitors each year In March 2012 PHMSA contracted ORNL to conduct the automatic shutdown (ASV) and remote controlled (RCV) valve study Oak Ridge National Laboratory (ORNL)

  3. Background ORNL’s Study Requirements of the Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011, Section 4 – Automatic/Remote-Controlled Shut-off Valves: • Requires that the Secretary mandate, by regulation, ASV/RCV be installed on newly constructed or entirely replaced natural gas and hazardous liquid transmission pipelines 2 years after the act was issued • Requires the Comptroller General to conduct a study on the ability of liquid and gas transmission pipeline operators to respond to a release within an HCA NTSB Recommendation P-11-11 (San Bruno): • Directly require that automatic shutoff valves (ASV) or remote control valves (RCV) be installed in high consequence areas and in Class 3 and 4 locations and spaced at intervals that consider population factors listed in regulations for gas transmission pipelines.

  4. Background ORNL’s Study March 28, 2012 Understanding the Application of Automatic Control and Remote Control Valves Workshop conducted • Federal and State regulators, transmission line operators, and the public discussed the practical considerations involved with installing, operating and maintaining ASV/RCV • Information obtained through the workshop was used by ORNL within their study • Meeting Website, including Summary Report: https://primis.phmsa.dot.gov/meetings/MtgHome.mtg?mtg=75 • Comments were submitted in request to address the scope of ORNL’s study • Federal Register Comments on commissioned valve study PHMSA-2012-0021: http://www.regulations.gov

  5. Background ORNL’s Study July 18 and 19, 2012 Government/Industry Pipeline Research and Development (R&D) Forum • Working group indicated a technology gap in the reliability of the operation of ASV • Based on the R&D forum recommendations a project is sought to study more accurate line break detection systems to minimize unintended valve closures • Forum Summary Report and Presentations: https://primis.phmsa.dot.gov/rd/mtg_071812.htm • Research Announcement: http://primis.phmsa.dot.gov/matrix/RfpInfo.rdm?rfp=41 • Solicitation closed, white papers currently being reviewed

  6. Comments on ORNL’s Draft Study On October 5th, 2012 ORNL presented in a webinar their draft study Comments were received from October 5 to October 26, 2012 on ORNL’s draft report There were seven commenters ORNL determined there were 42 technically substantive comments. Some of which resulted in a changes by ORNL to ORNL’s Study ORNL’s draft final report and comments to the ORNL study can be found on the meeting website: https://primis.phmsa.dot.gov/meetings/DocHome.mtg?Doc=9

  7. Changes Made to ORNL’s Study

  8. Changes Made to ORNL’s Study

  9. ORNL ASV/RCV Study Analyzed the response of rapid block valve closure on • Gas transmission lines with ignition of product • Hazardous liquid transmission lines with ignition of product • Hazardous liquid transmission lines without ignition of product Technical, operational, and economic feasibility were evaluated for ASV/RCVs • Fire modeling was used to establish metrics for analyzing response time for transmission lines with ignition • Basic Oil Spill Cost Estimation Model (BOSCEM) used by EPA on oil spill was used to model response time for HL transmission lines without ignition

  10. ORNL’s Study Observations ASVs/RCVs installation on newly constructed/fully replaced gas and liquid transmission lines are technically, operationally, and economically feasible (positive cost benefit). Decreasing the total volume of released product reduces overall impacts on public and environmental safety. Installing ASVs/RCVs can potentially be an effective strategy to mitigate consequences of unintended pipeline releases. Block valve closure swiftness is most effective in mitigating damage resulting from a pipeline release (and subsequent fire) when damaged pipeline segment is isolated and thermal radiation produced by fire declines in time to enable emergency responders to safely start fire fighting activities immediately upon arrival.

  11. ORNL’s Study Observations Positive effects of rapid block valve closure are only realized through combined efforts of pipeline operators and emergency responders. Similarly, the avoided cost of socioeconomic and environmental damage for hazardous liquid pipeline releases without ignition increase as time required to isolate the damaged pipeline segment decreases. The modeling is dependent on a case-by-case analysis of each pipeline system due to complexity of location, response capabilities, pipeline configuration, and resources

  12. Thank you