Xpress Downtown Atlanta Rerouting November 9, 2011. Xpress Atlanta Downtown Rerouting. Atlanta Streetcar Routing. Xpress Atlanta Downtown Rerouting Issues. Atlanta Streetcar Utility Relocation and Construction Begins December 1, 2011

gilon
Download Presentation

Xpress Downtown Atlanta Rerouting November 9, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Xpress Downtown Atlanta Rerouting November 9, 2011

  2. Xpress Atlanta Downtown Rerouting Atlanta Streetcar Routing

  3. Xpress Atlanta Downtown Rerouting Issues • Atlanta Streetcar Utility Relocation and Construction Begins December 1, 2011 • MARTA, CCT, GCT, and Xpress all have routing conflicts on Peachtree Street and around Woodruff Park • Riders on all systems affected • MARTA: will detour the three routes that use Peachtree Street during the time of construction • Xpress: all downtown Atlanta service (67% of total Xpress service, permanent rerouting) • GCT: all downtown service, permanent rerouting – Xpress East plan • CCT: all downtown service, permanent rerouting – CCT plan • Federal Center, Capitol Hill, Peachtree Center riders minimally affected • Woodruff Park, Fairlie-Poplar and Georgia Pacific riders have two – five block extra walk am and pm • Civic Center MARTA Station customers will use east routing – west routing does not travel to Civic

  4. 15 of 25 Xpress downtown routes will use East Side Alignment Applies to service from 11 of 12 counties

  5. 10 of 25 Xpress downtown routes will use West Side Alignment Applies to service from 9 of 12 counties

  6. Xpress Downtown Rerouting Timeline • September 15, 2011 GRTA given notice by City of Atlanta to relocate routes to accommodate Streetcar construction (utility relocation begins Dec. 1) • October 24, 2011 – November 23 Public Comment Period (including Open House meetings) • March 2012 Rerouting Plan implemented • October 2011GRTA transit staff develops East/West Routing Plan based on previous agreement with City • December 14, 2011 GRTA Board will vote on Final Rerouting Plan