crabs cavities @ ip4 boundary conditions
Download
Skip this Video
Download Presentation
Crabs cavities @ IP4? Boundary Conditions

Loading in 2 Seconds...

play fullscreen
1 / 13

Crabs cavities @ IP4? Boundary Conditions - PowerPoint PPT Presentation


  • 120 Views
  • Uploaded on

Crabs cavities @ IP4? Boundary Conditions. O.Brunner LHC-CC09. Objectives of the “investigation”. Is there any possibility to install one crab cavity module (assuming same size as one LHC ACS cavity) on each side of IP4? Where? Is it possible to connect the crabs to the cryogenic system?

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Crabs cavities @ IP4? Boundary Conditions ' - gezana


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
objectives of the investigation
Objectives of the “investigation”
  • Is there any possibility to install one crab cavity module (assuming same size as one LHC ACS cavity) on each side of IP4? Where?
  • Is it possible to connect the crabs to the cryogenic system?
  • Where to install crab power stations, the power lines, the control&LLRF systems?
where crabs could be installed
Where Crabs could be installed?
  • Only two options to fit the crabs around IP4:
    • ACN cavities region:
      • In case these cavities are not (all?) installed
    • The spare damper position:
      • In case the spare dampers doesn’t need to be installed
  • If both the ACN and the spare damper need to be installed (only LHC operation will tell us…see next talk), there will be no possibility to install crab cavities at IP4.
ir4 layout
IR4 layout

Point 5

  • Symmetric towards point 3
      • Not possible to free space in the ACN cavities region (power lines, RF couplers, access behind the ACN)
  • Max 3m longitudinally

IP4

QRL

ACS jumper

BPMs

SPARE ADT

ADT

ACN

ACS cavities

3-4m

≈10m

adt reserved space 3 4m
ADT Reserved Space ≈3-4m

Right of IP4

Left of IP4

Cryostat: max ≈ 3m longitudinally

lateral constraints
Lateral constraints
  • Space between Beam1 & Beam2: 420mm
  • Space between Beam2 & QRL: 380 - 450 mm (no bellows/bellows/bumps…)
how to feed the crabs with lhe
How to feed the crabs with LHe?
  • Two options (see B. Vullierme’s talk)
    • Extension of the SC cavity (main RF) LHe lines
      • Is it feasible? And how?
      • Does this require de-installing the SC cavity modules or any other systems?
      • Any impact on main RF operation ?
      • Will this limit the CC operating temperature to 4.5 K?
    • Specific cryogenic lines
      • Detailed integration study and installation of a dedicated jumper must be studied.
      • Any impact on QRL diameter? And therefore on CC cryostat?
      • Requires de-installation of beam lines equipment, cutting off of the QRL..
how to power the crabs
How to power the crabs?
  • CC could be powered by a 60kW RF power station located in the UL’s
      • How many square meters required?
      • Restricted space available in the Ul’s (possible conflict with the ACN power stations)

Need detailed integration study (very busy area) of:

    • the power station + control systems
    • LLRF (partially installed in SR4 (surface building))+ RF cabling
    • the power lines
    • services (water cooling, electricity (380V),…)
slide10

IP4

ARC 34

ACS jumper

ACS cavities

APWs

SPARE ADT

ADT

ACN

ACN power

Crab power?

≈10-15m2

slide11

General view (IP4 left)

ACN power

ACN power

very rough cost estimate per cavity
Very rough cost estimate (per cavity)
  • Civil Engineering: ≈ 10kCHF
  • Cabling (controls): ≈ 40kCHF
  • Water cooling: ≈ 30kCHF
  • RF cabling: ≈ 150kCHF
  • RF power lines (50m): ≈ 100kCHF
  • Interlock & Control system: ≈ 80kCHF
  • Low Level RF ≈ 125kCHF
  • Installation: ≈ 90kCHF
conclusion
Conclusion
  • Very few possibilities to host the crab cavities at IP4.
    • Spare damper
    • ACN cavities
  • No way to install the CC at IP4 in case both the spare dampers AND the ACN cavities are needed for future operation
  • Feeding the crabs with Lhe at P4 looks possible. More detailed study is required.
  • There is a possibility to install dedicated RF power stations in the UL’s. Detailed integration study needed.
  • LLRF and control systems could be installed either in the UL’s or in the SR4 (surface building)
ad