An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EIP & NASDAT Status 5/24/2011

  2. Status • CDR Delayed • EIP is nominally ready for CDR, NASDAT requires more time • Rescheduled combined CDR date: 8/9/11 • EIP requires ~3 months for Production • The current gates to EIP Production build: • Functional & Environmental Testing (6/20/11) • Design revision / drawings updated • Schematic/layout level peer review • Separate program-level CDR? (discuss)

  3. Status • EIP Pre-Production (2 units) • All subassemblies tested • 1 EIP built in-house & delivered to assembly vendor for build of 2nd EIP • Receipt of EIP & box testing late this week • Units will be fully functional but non-flight • Need to “steal” one production unit for Qualification test; final flight unit delivery is now 34 units

  4. Status • EIP Errors Found: • Internal cable lengths / clearance issues • Minor PCB layout errors – mirrored/rotated items • Design revisions in process • Production Assembly: 8/18-9/21 (34 units)

  5. Status • NASDAT Pre-Production (1 unit) • Enclosure in hand • All Connectors & COTS PCBs in hand • Cable routing & mechanical plan complete • Custom PCBs in fab & final design stages • Defined MICD with aircraft • Pinouts defined; document in process • Initial fit check with ER-2 completed • Unit Assembly: 6/7-8/2 • Environmental Test: 8/26-9/15

  6. Status • Insert NASDAT box & model images here

  7. Status • NASDAT Interface Card: 12 Layers • Status: In assembly

  8. Status • NASDAT PDU Card: Design 75% • Expected completion date: 5/27/11 • NASDAT Analog Card: • Vendor selected, in UC purchasing system • NASDAT Iridium Power Card: • Design complete, out for bid

  9. Status • Aircraft & Network: • 25 Bulkheads purchased – enough for ER-2, WB-57 & GH • Purchased ethernet cable, connectors, & experiment-side connectors for all EIPs • 5/17/11 – ER-2 Aircraft Installation Meeting • Follow-up meeting in ~July • Pre-Production EIP & ER-2 ground test planned • Little or no changes required to cockpit switch panel or EIP ship-side interface.