An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q1 2007 Engineering Review INSP – Instrument Support

  2. Highlights (Q1/2007) • Found a lost LBC Red • Worried about where to run the cooling lines from 4th floor helium compressors to the instrument platform LBT Q1 2007 Engineering Review

  3. Open Issues • Technical • Need better metrology tools • Routing of helium lines • Where does LBTI’s compressor go? • Schedule • None • Financial • None • Resource • Mountain manpower availability LBT Q1 2007 Engineering Review

  4. Progress (Q1/2007) In addition to the Highlights • Clearance between LBC and Secondary – Took J. Little’s measurements, and transformed them into Δz clearance • There is plenty of clearance LBT Q1 2007 Engineering Review

  5. Planning (Q2/2007) • Werner Laun from Heidelberg is coming in May to route dummy lines from the 4th floor to the instrument platform LBT Q1 2007 Engineering Review

  6. Lucifer & LINC 4th Floor Hardware LBT Q1 2007 Engineering Review