LBT Q1 2007 Engineering Review. MCSC Mount Control System. Highlights (Q1/2007). No planned work during Q1/2007 ELFR motor brushes failed March 15, damaging the motor windings. The motor is now operational but winding damage may impact its lifespan. Open Issues. Technical

brick
Download Presentation

LBT Q1 2007 Engineering Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBT Q1 2007 Engineering Review MCSC Mount Control System

  2. Highlights (Q1/2007) • No planned work during Q1/2007 • ELFR motor brushes failed March 15, damaging the motor windings. The motor is now operational but winding damage may impact its lifespan. LBT Q1 2007 Engineering Review

  3. Open Issues • Technical • Azimuth main encoder • Installation of remaining elevation main encoder read heads • Motor encoder jumps • Occasional unexplained elevation tracking errors • ELFR motor winding damage • All brushes must be inspected and replaced if necessary • Schedule • None • Financial • None • Resource • MCS competing for resources against rotator development effort • Unable to access elevation motors due to safety concerns LBT Q1 2007 Engineering Review

  4. Progress (Q1/2007) • Unexplained elevation tracking errors now appear to be linked to the HBS runout • Encoder jumps have apparently subsided since ELFR motor brush replacement LBT Q1 2007 Engineering Review

  5. Planning (Q2/2007) • April 25 : • Azimuth main encoder review • May 14 : • Farrand Controls visits • May 22 : • Elevation encoder heads installed • May 21-24 : • Elevation and azimuth motor encoder tests • Azimuth and elevation servo maintenance • TBD: • Elevation motor brush inspection and replacement • TBD: • Azimuth main encoder rework LBT Q1 2007 Engineering Review