Yellowtail Flood Pool Reallocation Study

Yellowtail Flood Pool Reallocation Study. Travis D. Yonts Water Resource Engineer U.S. Army Corps of Engineers Omaha, Nebraska. Bighorn River System Issues Group July 29, 2008. Presentation Overview. Project background Computer simulation efforts What has been done to this point?

china
Download Presentation

Yellowtail Flood Pool Reallocation Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Yellowtail Flood PoolReallocation Study Travis D. Yonts Water Resource Engineer U.S. Army Corps of Engineers Omaha, Nebraska Bighorn River System Issues Group July 29, 2008

  2. Presentation Overview • Project background • Computer simulation efforts • What has been done to this point? • What’s next? • Questions

  3. Evaluate the change in flood reduction benefits due to reallocation of flood control storage to joint use storage for Yellowtail Dam and Bighorn Lake. Project Objective

  4. BIGHORN LAKE STORAGE ALLOCATION Dam Crest Elev. 3660.0 3657 (1,328,360 AF) Surcharge - 52,829 Acre-Feet Exclusive Flood Control - 258,331 Acre - Feet 3640 (1,070,029 Acre - Feet) Joint Use - 240,342 Acre - Feet 3614 (829,687 Acre - Feet) Active Conservation - 336,103 Acre - Feet Top of Conservation Elev. 3547.00 (493,584 Acre - Feet) Inactive Conservation - 477,576 Acre - Feet Top of Dead Elev. 3296.50 (16,008 Acre - Feet) Dead - 16,008 Acre - Feet

  5. PROPOSED STORAGE ALLOCATION Dam Crest Elev. 3660.0 3657 (1,328,360 AF) Surcharge - 52,829 Acre-Feet Exclusive Flood Control - 190,846 Acre - Feet 3645 (1,137,514 Acre - Feet) Joint Use - 307,827 Acre - Feet 3614 (829,687 Acre - Feet) Active Conservation - 336,103 Acre - Feet Top of Conservation Elev. 3547.00 (493,584 Acre - Feet) Inactive Conservation - 477,576 Acre - Feet Top of Dead Elev. 3296.50 (16,008 Acre - Feet) Dead - 16,008 Acre - Feet

  6. HEC-ResSim(Reservoir Evaluation System-Simulation) • Single or multiple reservoir systems • Flood control • Hydropower • Water supply (M&I, irrigation, etc) • Diversions • Navigation • Flow targets (max & min) • POR or event simulation

  7. Data Requirements • Daily stream flow 1967-2007 • Daily reservoir inflow, outflow, storage • Daily precipitation, evaporation • Elevation-area-capacity relationships • Spillway & outlet rating curves • Downstream discharge-damage functions • Reservoir operating criteria/storage zones • Project design floods • Local flow calculations

  8. Yellowtail Downstream Control Points Sidney Miles City Yellowstone River Bighorn Billings Bighorn River St. Xavier Bighorn Lake

  9. Example ResSim Outputs • Reservoir elevation • Reservoir releases • Flows at downstream control points

  10. What’s next? • Continue ResSim model calibration. • Perform baseline ResSim simulation. • Current conditions • Perform proposed ResSim simulation. • Include 5 ft pool raise