June 8, 2011 Irvine Unified School District. Deerfield Elementary School Modernization. What is a Modernization?. Eligibility Permanent buildings - 25 years old Portable buildings - 20 years old DSA Requirements ADA Compliance Fire, Life, Safety Upgrades Maintenance Requirements.

Download Presentation

Deerfield Elementary School Modernization

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


June 8, 2011

Irvine Unified School District

Deerfield Elementary SchoolModernization


What is a Modernization?

  • Eligibility

    • Permanent buildings - 25 years old

    • Portable buildings - 20 years old

  • DSA Requirements

    • ADA Compliance

    • Fire, Life, Safety Upgrades

  • Maintenance Requirements


Budget and Funding

  • Board Approved Project Budget

    • Construction Costs

    • Soft Costs

      • Architect Fees

      • Agency Fees (DSA, Health Dept., IRWD, etc.)

      • Testing and Inspection Fees

    • $12,600,000 ($12.6m)

      • Anticipated State Funding: $3,992,966

      • Local Matching Funds: $8,607,034


Planned Scope of Work: DSA Requirements

  • Required Fire Life Safety/ADA Compliance/Structural components:

    • Upgrade restrooms to ADA compliance

    • Add restroom fixtures based on student and staff capacity

    • Upgrade drinking fountains for ADA compliance

    • Upgrade fire alarm system

    • Upgrade ADA accessible parking stalls

    • Upgrade path of travel (exterior)

    • Upgrade/create updated exiting

    • Loss of mezzanine/pit areas and current teachers lounge

    • Relocation/replacement of shade structure

    • Relocation/replacement of current classroom relocatables


Planned Scope of Work:Maintenance Needs

  • Scope includes:

    • Roof replacement

    • Flooring replacement

    • New PA/Clock system

    • Electrical upgrade

    • Paint all interior/exterior surfaces

    • HVAC control replacement


Pre-Modernization Site Plan


Exterior Photos


Pre-Modernization Floor Plan


Post-Modernization Floor Plan


Kindergarten


Classroom


Media Center


Support Space


Pull Out Spaces/Small Group Instruction


Multi-Purpose Room


New Entry


New Administration Floor Plan


Administration


Kinder Play Area


New Classroom Building


New Classroom Layout


New Classroom


Timeline

  • Moving In

    • By September 1, 2011*

  • Construction

    • Phase I

      • Complete

    • Phase II

      • January 3, 2011- August 19, 2011


Questions

Thank you for your continued support of the

Deerfield Elementary School students!