Deerfield Elementary School Modernization

May 6, 2010 Irvine Unified School District HMC Architects. Deerfield Elementary School Modernization. What is a Modernization?. Eligibility Permanent buildings - 25 years old Portable buildings - 20 years old DSA Requirements ADA Compliance Fire, Life, Safety Upgrades

becka
Download Presentation

Deerfield Elementary School Modernization

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. May 6, 2010 Irvine Unified School District HMC Architects Deerfield Elementary SchoolModernization

  2. What is a Modernization? • Eligibility • Permanent buildings - 25 years old • Portable buildings - 20 years old • DSA Requirements • ADA Compliance • Fire, Life, Safety Upgrades • Maintenance Requirements

  3. Budget and Funding • Board Approved Project Budget • Construction Costs • Soft Costs • Architect Fees • Agency Fees (DSA, Health Dept., IRWD, etc.) • Testing and Inspection Fees • $12,600,000 ($12.6m) • Anticipated State Funding: $3,992,966 • Local Matching Funds: $8,607,034

  4. Planned Scope of Work: DSA Requirements • Required Fire Life Safety/ADA Compliance/Structural components: • Upgrade restrooms to ADA compliance • Add restroom fixtures based on student and staff capacity • Upgrade drinking fountains for ADA compliance • Upgrade fire alarm system • Upgrade ADA accessible parking stalls • Upgrade path of travel (exterior) • Upgrade/create updated exiting • Loss of mezzanine/pit areas and current teachers lounge • Relocation/replacement of shade structure • Relocation/replacement of current classroom relocatables

  5. Planned Scope of Work:Maintenance Needs • Scope includes: • Roof replacement • Flooring replacement • New PA/Clock system • Electrical upgrade • Paint all interior/exterior surfaces • HVAC control replacement

  6. Pre-Modernization Site Plan

  7. Pre-Modernization Floor Plan

  8. Post-Modernization Floor Plan

  9. New Administration Floor Plan

  10. New Classroom Layout

  11. Interim Housing: El Camino • Board Approved Transportation Zone • Interior • Wall restoration • Carpet repair/patch • Paint • Plumbing • Exterior • Asphalt, concrete • Playground • Childcare Restroom Facility • Street Signs • Install approximately one-two weeks prior to start of school

  12. Interim Housing: El Camino Real

  13. Deerfield to El Camino

  14. Childcare • CDC • Closed Friday, June 25th* • Reopens at El Camino Monday, June 28th* • See CDC for more information regarding childcare and availability

  15. Timeline • Moving Out • Teachers - Friday, June 25th • Administration staff - Wednesday, June 30th • Moving In • By September 1, 2011* • Construction • Phase I • July 12, 2010 - December 31,2010 • Phase II • January 3, 2011- August 19, 2011

  16. Questions Thank you for your continued support of the Deerfield Elementary School students!