1 / 13

FIRE Design: FY03 PFC Tasks

FIRE Design: FY03 PFC Tasks. NSO PAC Meeting San Diego, February 27-28, 2003. Mike Ulrickson (FIRE Divertor Design Team) presented by Richard Nygren (new member, NSO PAC) Sandia National Laboratories.

adaniels
Download Presentation

FIRE Design: FY03 PFC Tasks

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FIRE Design: FY03 PFC Tasks NSO PAC Meeting San Diego, February 27-28, 2003 Mike Ulrickson (FIRE Divertor Design Team) presented by Richard Nygren (new member, NSO PAC) Sandia National Laboratories Sandia is a multiprogram laboratory operated by Sandia Corporation, a Lockheed Martin Company,for the United States Department of Energy under contract DE-AC04-94AL85000.

  2. Introduction • Best guess for readiness for PVR is late August or early September 2003. • Continuing resolution in FY03 has constrained the initial schedule. • In the following slides: green textindicates completed tasks, blue textindicates tasks in progress, black text indicates planned tasks that can be done with the FY03 budget.

  3. Plasma Equilibrium green (completed) • Define baseline plasma shape for 2.14 m. • Use TSC to compute vertical and radial disruption cases. • Define the range of , li, , and Paux that should be accommodated and provide magnetic data. black text (can be done with FY03 $$)

  4. Edge modeling • Use UEDGE to reestablish edge plasma conditions with the proper fusion power and heating • Determine heat flux profiles • Determine boundaries for partial detachment blue(in progress) black text (can be done with FY03 $$) Note: for high density plasma in ARIES-RS/CLIFF for APEX, Rognlien found steady state solution for strongly radiating regions near X-point.

  5. Disruption Forces • Rebuild OPERA model of vessel and PFCs including copper(input from design at Boeing) • Use TSC data as input to Opera to find eddy currents and forces • Use Opera to determine the effect of the copper shell on magnetic diagnostics • Run a vertical disruption case to compare to vertical disruption on 2.0 m machine and use results to scale radial disruption forces to 2.14 m

  6. Design • Revise baseline divertor design (input to Opera) • Revise the divertor hardware to accommodate the new plasmas and check shape variations • Compute stresses in the revised design for both thermal and disruption loads (input from Opera) • Revise design as needed to accommodate stresses green (completed) black text (can be done with FY03 $$)

  7. Heat flux testing • Investigate new concept for W rod attachment to improve reliability (PFC base program but input from FIRE design) • New design completed • Negotiating with vendor for production green (completed) black text (can be done with FY03 $$)

  8. W-rod Armor • Mockups have survived high heat flux tests to 24MW/m2 and thermal cycling for 500 cycles*. • We recommend two design improvements. - Creep resistant Cu alloy as the rod bed. - Positive mechanical lock of rod to bed (grooved rod tip). Vendor bids have been received. *PW-8 rods reached 3300oC at 24MW/m2. Some erosion of rods occurred but no cracking or melting. PW-8 was then subjected to thermal fatigue cycles After 370 cycles (10s-ON:10s-OFF) at 20MW/m2, one rod began to melt. The affected area grew to 9 rods; we terminated testing at 500 cycles.

  9. ELMs on FIRE ELMS are not a problem if no surface melting occurs. We must reduce the magnitude of ELMS. • Most of the 2% cases and a few 5% cases are acceptable. • Limit for 0.1ms ELM is ~0.3 MJ/m2(partially detached, 12 MW/m2) • Limit for 1.0ms ELM is ~1.0 MJ/m2(partially detached, 12 MW/m2) • Assumptions for ELM energy deposited on FIRE divertor plates. • Either (a) 2% or (b) 5% of stored energy is lost. • Footprint for deposition is either (a) same as normal operation or (b) up to three times larger • Duration of ELM is 0.1<tELM<1ms

  10. ELMs Melting LIMIT Melting will not occur when the deposited energy density is less thanthe value at the intersection of (a) T-rise curve and (b) TLIMIT,normalHF. T-rise (1ms ELM) 5% (loss Estored) 6MW/m2 q”normal Energy Density >1.25MJ/m2 to avoid melting.

  11. PFC Task Progress

  12. Reporting • Provide data needed for Physics Validation Review • Revise divertor section of engineering report to include new design

  13. Summary • A redesign of the PFC components can be completed in time for the PVR, but the effort must start immediately. • Funding is not adequate for iterating the divertor design. • We can only scale the design to the new size and analyze the forces • Local areas of excessive stress are likely to exist on the supports or vacuum vessel

More Related