SWEA sensor FM model work remaining before delivery

SWEA sensor FM model work remaining before delivery. Spare boards preparation (4 days ) Operations tested on spare boards first (to be then applied to FM boards ) - To check procedures on spare boards first and to apply then to FM

zorana
Download Presentation

SWEA sensor FM model work remaining before delivery

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SWEA sensor FM model workremainingbeforedelivery MAVEN-Swea sensor pre-shipping review - December 1-2/2011

  2. Spareboardspreparation(4 days) • Operations tested on spareboardsfirst (to bethenapplied to FM boards ) • - To check procedures on spareboards first and to applythen to FM • - To check UV exposition in order to reduce micro-bio contamination • Modification amplifiersboard and shunt JP2 on HVPS board – 2 hours – Microtec • Cleaning HVPS board A withsterile IPA – 2 hours – IRAP • Sticking , coatingspareboards plus harness – 0,5 day – IRAP • Drying, outgassing in thermal chamber – 1 night - IRAP • Functionnal test – 2 hours – IRAP • Storingboards in primary vacuum MAVEN-Swea sensor pre-shipping review - December 1-2/2011

  3. FM model preparation and conditionning (7 days) • FM boardsdisassemblingafterdecember 3rd (facility/operator not available) • FM boardsdisassembly - 2 hours - IRAP • Re-work HVPS boardharness – 1 day - Microtec • Functionnal test on HVPS board – 2 hours - IRAP • Boardscleaningwithsterile IPA and driedwith dry nitrogen – 2 hours – IRAP • Exposition of boards to UV lamp (germicide) – 2 hours - IRAP • Coating parts & harness on boards – 1 day – IRAP • Boardsdrying & outgassing - 1 night - IRAP • Micro-bio assay on FM boards and insideboardshousing (to bedelivered to SSL) • Instrument assembly, screwstorqued – 1 day – Comat/ Microtec/ IRAP • Instrument storage in primary vacuum - IRAP • Assemble Sweasensorwithcoated and outgassed FM boards • End of calibrations in vacuum chamber • Swea FM sensorready • Storage in vacuum chamber MAVEN-Swea sensor pre-shipping review - December 1-2/2011

  4. Purging adaptation (JR)Swea team has to provide a purging adaptation to fit in SSL purging system - Weneed to know the interface on SSL side and the tube length on Sweasensorside - On IRAP side : SWAGELOK type SS-QC4-D-400 (to bediscussedwith SSL) MAVEN-Swea sensor pre-shipping review - December 1-2/2011

  5. Log books to beappendedShipping plans and documents: Shouldweask for definitive or temporary exportation to the USA for FM sensor?Will Sweasensorbe sent back to IRAP in case of big trouble or willitberepairedat SSL? MAVEN-Swea sensor pre-shipping review - December 1-2/2011

  6. pinpuller Top cover Top deflector Externalgrid obturator bottomdeflector Internalgrid Ribs (6) Ext. hemisphere Int. hemisphere MCPs + holder Anode board Boardshousing Amplifiersboard Shield Purging tube HVPS board Sweasensorcutoff MAVEN-Swea sensor pre-shipping review - December 1-2/2011