1 / 18

Joint Legislative Audit & Review Committee January 5, 2011 David Dean, JLARC Staff

State Ferry Terminals: Procedures to Account for and Request Capital Funds Have Improved, but Additional Actions Are Needed. Preliminary Report. Joint Legislative Audit & Review Committee January 5, 2011 David Dean, JLARC Staff. Presentation Overview. Background

zasha
Download Presentation

Joint Legislative Audit & Review Committee January 5, 2011 David Dean, JLARC Staff

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. State Ferry Terminals:Procedures to Account for and Request Capital Funds Have Improved, but Additional Actions Are Needed Preliminary Report Joint Legislative Audit & Review Committee January 5, 2011 David Dean, JLARC Staff

  2. Presentation Overview • Background • Results of previous legislative study • New statutory requirements • Audit results • Progress made in implementing new requirements • Additional actions needed • Recommendation State Ferry Terminals

  3. 1 Background

  4. Legislature Sought Improved Information on State Ferry Finances • In 2006, the State Ferries Division of the Washington Department of Transportation proposed a $5.6 billion long-range plan • In response, the Legislature directed the Joint Transportation Committee (JTC) to study ferry finances • JTC contracted for work, which focused initially on the capital needs for ferry terminals State Ferry Terminals Report Page 3

  5. JTC Consultant Identified Concerns About Terminal Facility Repair Plans • JTC’s consultant found State Ferries had requested capital funds for terminals that were still in good condition • State Ferries’ definitions of project categories overlapped & created confusion • Consultant found all systemwide projects were allocated to preservation, overstating the true cost of the preservation program • Life-cycle cost model was not updated for current asset conditions State Ferry Terminals Report Page 4

  6. Legislature Responded by Adding Several New Statutory Requirements • Directing OFM to develop key definitions • Prohibiting the use of capital funds for maintenance • Directing State Ferries to allocate systemwide and administrative costs to specific capital projects • Requiring State Ferries to maintain a life-cycle cost model to identify investments needed to ensure terminals are preserved State Ferry Terminals Report Page 4

  7. Legislature Responded by Adding New Statutory Requirements (cont.) • Specifying appropriations made for “preservation” be spent only on preserving assets and only when warranted by asset condition • Requiring State Ferries to use its life-cycle cost model as the basis for preservation budget requests • Directing JLARC to assess State Ferries’ progress in implementing the new statutory requirements State Ferry Terminals Report Page 5

  8. 2 Audit Results

  9. Progress Made in Implementing New Statutory Requirements • OFM issued required definitions of preservation, improvement, & maintenance • State Ferries revised its capital budget request procedures to exclude maintenance from the capital program • State Ferries developed a new approach to allocate systemwide & administrative costs • State Ferries updated life-cycle cost model for terminals. State Ferry Terminals Report Page 5

  10. State Ferries Has Not Fully Complied with New Requirements • WSDOT did not provide information in its project budget requests that clearly identified the condition of the individual ferry terminal assets • Records show State Ferries used preservation funds for assets that were in good or fair condition, or were not rated • Found 9 of 15 projects on the 2009-2011 project list included the early replacement or renovation of assets State Ferry Terminals Report Page 6

  11. JLARC Analyzed Ferry Terminal Projects Approved for 2009-11 Asset Condition Good, Fair, or Not Rated $32.5 M • Asset Condition Poor or Substandard $13.5 M 29% 71% Total: $46.0 M Source: JLARC analysis of ferry terminal preservation projects approved for 2009-2011. State Ferry Terminals Report Page 6

  12. State Ferries Suggests Two Primary Justifications for Early Replacements • State Ferries explains early replacement of some structures is necessary when some components of a system are due for replacement but other closely related components are not • State Ferries asserts preservation work is warranted on some structures that are still in good or fair condition because allowing further deterioration could result in a structural or safety concern State Ferry Terminals Report Pages 7-8

  13. State Ferries Suggests Two Primary Justifications for Early Replacements • JLARC concluded that while State Ferries’ justifications may be reasonable, to comply with statute they should more fully disclose condition information to the Legislature. State Ferry Terminals Report Pages 7-8

  14. 3 Conclusions & Recommendation

  15. Overall Conclusions • Capital planning for terminal preservation has improved in response to legislative requirements • Additional actions are needed to comply with statute and enhance transparency and accountability • Actions needed to ensure the Legislature receives appropriately detailed information when considering funding requests. State Ferry Terminals Report Page 8

  16. Recommendation • WSDOT, working in collaboration with OFM, should develop new procedures for providing more informative capital budget requests for State Ferry terminal preservation State Ferry Terminals Report Page 8

  17. Recommendation (cont.) • New procedures should require: • Updating the life-cycle cost model so that it explains the majority of budget requests • Including asset condition ratings with capital budget requests • Providing justification for exceptions to replace or renovate assets that are not justified solely by asset condition State Ferry Terminals Report Page 8

  18. Contact Information Proposed Final Report: Next scheduled JLARC meeting (tentative - May) David Dean 360-786-5293 david.dean@leg.wa.gov www.jlarc.leg.wa.gov State Ferry Terminals

More Related