This chapter focuses on the crucial process of assigning resources to activities in project management. After creating the project and defining resources, the next step is to allocate these resources effectively. To begin, ensure that all tasks are set to 'Fixed Duration' in the Task Information window. A detailed table lists the resources that should connect to specific activities. The assignment process involves selecting an activity, followed by the resources needed, and adjusting their units as necessary to optimize project outcomes.
E N D
Project Manegment(IENG419) Fall:(2010-2011)Research Assistants: Farhad Mousavi & Sadegh Niroomand
Chapter4 Assigning Resources to Activities If you followed previous chapters and created the project and also defined resources, so you are ready to assign the resources to the activities.
Assigning Resources to Activities • Before starting to assign, for all tasks, from Task Information window, we should change the Task Type to Fixed Duration as you see here 2 3 1 4 5
Assigning Resources to Activities • This table shows that which resources should be connected to the activities.
Assigning Resources to Activities • To start, we follow this order: 1 Select an activity 2
Assigning Resources to Activities • Now in Assign Resources window, we can select resources to assign to the selected activity. You can change units 2 1 Select