1 / 2

Proton Source Shutdown Schedule

Proton Source Shutdown Schedule. Prep L6 and L3 for collimator placement. BOOSTER OFF- Cool down and miscellaneous prep work. Collimators (with ironworkers) – Assumes collimators have been assembled in access bay!. Lambertson (LInac Tunnel). EDWA Installation.

werner
Download Presentation

Proton Source Shutdown Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proton Source Shutdown Schedule Prep L6 and L3 for collimator placement BOOSTER OFF- Cool down and miscellaneous prep work Collimators (with ironworkers) – Assumes collimators have been assembled in access bay! Lambertson (LInac Tunnel) EDWA Installation Collimators (ironworkers move to EDWA installation) Lambertson (LInac Tunnel) EDWA Installation Lambertson (LInac Tunnel) Dogleg Modification at Long 3 EDWA Installation Install Damper Cavity EDWA Installation

  2. Shutdown Schedule (cont’d) Commissioning and Studies. Test MI-8 extraction on weekend. Install Prototype RF Cavities Vertically align Booster Commissioning and Studies. Possible weekend extraction tests. Return to normal operation

More Related