arlene
Uploaded by
7 SLIDES
253 VIEWS
90LIKES

Shutdown Schedule and Collimator Installation for Proton Source - August 2003

DESCRIPTION

This document outlines the shutdown schedule, installation of collimators, and various preparations related to the Proton Source in August 2003. It includes details on the movement of collimators to the EDWA installation site in the Linac Tunnel, as well as modifications to the dogleg at Long 3. The document also captures discussions from the Proton Source Meeting on August 8, 2003, addressing operational issues, such as beam performance at MiniBooNE and equipment changes that occurred during the shutdown.

1 / 7

Download Presentation

Shutdown Schedule and Collimator Installation for Proton Source - August 2003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Shutdown Schedule BOOSTER OFF- Cool down and miscellaneous prep work Collimators (with ironworkers) – Assumes collimators have been assembled in access bay! Lambertson (LInac Tunnel) EDWA Installation Collimators (ironworkers move to EDWA installation) Lambertson (LInac Tunnel) EDWA Installation Lambertson (LInac Tunnel) Dogleg Modification at Long 3 EDWA Installation Install Damper Cavity EDWA Installation Proton Source Meeting, August 8, 2003 – E. Prebys

  2. Shutdown Schedule (cont’d) Commissioning and Studies. Test MI-8 extraction. Shutdown to Install Prototype RF Cavities Commissioning and Studies. Possible off-hours beam to MiniBooNE Return to normal operation Proton Source Meeting, August 8, 2003 – E. Prebys

  3. How are we doing? Beam to MiniBooNE Total Output MH2 and Q10 supplies replaced Mid-March to Mid May: great running!!! What the hell has happened Proton Source Meeting, August 8, 2003 – E. Prebys

  4. When did we start having problems? Proton Source Meeting, August 8, 2003 – E. Prebys

  5. What Happened? • May 19th owl: • LRF3 Changed • “Studied the effect of various parameters on 4VELO” –LJA • May 21st afternoon: • Rested LRF5 • Changed module on debuncher water skid. Some problems bringing back up. • May 22nd owl: • KRF1 trip on CS fault • Tied of BRF4 to replace modulator • Problem was definitely there after the May 22nd owl shift Proton Source Meeting, August 8, 2003 – E. Prebys

  6. What’s Different Losses Compared to May 13 L3 and L15 Sometimes these are much more unstable L8 L15 Proton Source Meeting, August 8, 2003 – E. Prebys

  7. Injection Orbit Jitter? Consistent with Dp/p ~ .1% Proton Source Meeting, August 8, 2003 – E. Prebys

More Related
SlideServe
Audio
Live Player
Audio Wave
Play slide audio to activate visualizer