Investment costs in the virtual test
Download
1 / 8

Investment costs in the Virtual Test - PowerPoint PPT Presentation


  • 96 Views
  • Uploaded on

Investment costs in the Virtual Test. GRI NW Investment I1- Virtual Test/Business Simulation. Bas Barten Gas Transport Services. Virtual pipeline through 4 countries. Germany Netherlands Belgium France. 400 km. 400 km. 400 km. 400 km. 50 bar. 50 bar. 50 bar. 50 bar.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Investment costs in the Virtual Test' - verne


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Investment costs in the virtual test

Investment costs in the Virtual Test

GRI NW Investment I1-

Virtual Test/Business Simulation

Bas Barten

Gas Transport Services


Virtual pipeline through 4 countries
Virtual pipeline through 4 countries

Germany Netherlands Belgium France

400 km

400 km

400 km

400 km

50 bar

50 bar

50 bar

50 bar

50 bar


Virtual pipeline through 4 countries1
Virtual pipeline through 4 countries

Germany Netherlands Belgium France

400 km

400 km

400 km

400 km

50 bar

50 bar

50 bar

50 bar

50 bar

50 bar

80 bar


Investment costs for 48 inch
Investment costs for 48 inch

Yearly volume transported: 20 bcm

Capacity@7400 hours LF: 2,7 mln Nm3/h

CAPEX per country:

400 km 48 inch pipeline = 800 mln EUR

3 compressor stations ( each 35 MW) = 300 mln EUR

Total CAPEX per country = 1,1 billion EUR

OPEX per country:

OPEX for pipe and compressors = 21 mln EUR/year

Fuel cost for compressors = 67 mln EUR/year (7400 running hours per year)


Investment costs for 48 inch 36 inch
Investment costs for 48 inch (36 inch)

Yearly volume transported: 20 bcm (10 bcm)

Capacity@7400 hours LF: 2,7 mln Nm3/h (1,35 mln Nm3/h)

CAPEX per country:

400 km 48 inch pipeline = 800 mln EUR (560)

3 compressor stations = 300 mln EUR (200)

Total CAPEX per country = 1,1 billion EUR (760)

OPEX per country:

OPEX for pipe and compressors = 21 mln EUR/year (14)

Fuel cost for compressors = 67 mln EUR/year (7400 running hours per year) (34)


Investment costs remarks
Investment costs remarks

  • No overhead costs or general administration only direct OPEX (e.g maintenance and operation)

  • Costs reflect the range of investment costs of the TSOs in the active group (+/- 40 %) excluding tax

  • We think more accurate estimation is unnecessary at the moment and also not possible without complex studies taken into account the exact route of the pipeline

  • Fuel gas at gas price of 25 EUR/MWH

  • Are two pipeline diameters sufficient?


Investment costs in the virtual test

Investment costs for steps in between

  • 20 bcm and 10 bcm are at their “limit”

  • Other options can be expanded with adding Comp Stations