1 / 18

Replacement of Transformers EMT103/76, EMT305/76

Replacement of Transformers EMT103/76, EMT305/76. N. Latif 04/09/ 2019. Main Points. EMT103/76 Loads supplied by EBD1/76 Possibility of Re-Powering EMT305/76 Loads supplied by ERD1/76 Inspection Visit/VIC Proposed Duration/Sequence of Works Dismantling Transport Installation

vday
Download Presentation

Replacement of Transformers EMT103/76, EMT305/76

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Replacement of Transformers EMT103/76, EMT305/76 N. Latif 04/09/2019

  2. Main Points • EMT103/76 • Loads supplied by EBD1/76 • Possibility of Re-Powering • EMT305/76 • Loads supplied by ERD1/76 • Inspection Visit/VIC • Proposed Duration/Sequence of Works • Dismantling • Transport • Installation • Project Team • Co-activities/Risks Replacemnet of Transformers, LHC

  3. EMT103/76 Transformer will be ready for shipment on 25-09-19 Replacemnet of Transformers, LHC

  4. SLD: Loads supplied by EBD1/76 EMT103/76 supplies switchboard EBD1/76. Loads supplied from this switchboard are in UJ76, R76, RR73 andTZ76. Main loadsare lights, power sockets, monorail, repowering to some UPS/switchboards etc. Replacemnet of Transformers, LHC

  5. Possibility of re-powering EBD1/76 • Load on EBD1/76 = 95 A (average) • Load on ESD1/76 = 05 A (average) • Re-powering Link b/w EBD1/76 and ESD1/76 = 200A • All the loads can be re-supplied if load stays like this • If any user increases the load, then plan for load-shedding has to be defined. Replacemnet of Transformers, LHC

  6. EMT305/76 Transformer will be ready for shipment during week 44 Replacemnet of Transformers, LHC

  7. SLD: Loads supplied by ERD1/76 • EMT305/76 supplies switchboard ERD1/76. • This switchboard supply ERD1/73 (RR73) and ERD1/77 (RR77) • Load on ERD1/76 = 0 A • No re-powering available Replacemnet of Transformers, LHC

  8. Inspection Visit/VIC • Inspection Visit during EL maintenance Week (39) to have a look on LV/HV terminals and control connections • Participants: EN-EL-ENP, EN-EL-EIC, EN-EL-OP • Re-supplying the Loads of EBD1/76 from ESD1/76. (EN-EL-OP) • Electrical power lock-out of the transformer, then issue of work permits. (EN-EL-OP) • Removal of transformer casing front. (EN-EL-EIC) • Visual inspection of control cables, bar sheath, cable connection terminals, etc. No works planned. (EN-EL-EIC) • Re-installation of transformer envelope. (EN-EL-EIC) • Transformer energization. (EN-EL-OP) • VIC is planned in Week 37 on 12-09-2019 • Diagnostics of paint (for Lead) on 17-09-2019 Replacemnet of Transformers, LHC

  9. Duration/Sequence of works EMT103/76 Work Phase (Week 41, 07-10-2019 to 11-10-2019): • Participants: EN-EL-ENP, EN-EL-EIC, EN-EL-OP, EN-EL-MT, EN-HE, ARNOLD, COMSA. Replacemnet of Transformers, LHC

  10. Duration/Sequence of works EMT305/76 Work Phase (Week 47, 18-11-2019 to 2-11-2019): • Participants: EN-EL-ENP, EN-EL-EIC, EN-EL-OP, EN-EL-MT, EN-HE, ARNOLD, COMSA. Replacemnet of Transformers, LHC

  11. Dismantling • Re-supplying the Loads of EBD1/76 from ESD1/76. (EN-EL-OP) • Electrical power lock-out of the transformer, then issue of work permits. (EN-EL-OP) • Dismantling of boundary barriers. (COMSA) • Transformer envelope removal. (COMSA) • Disconnection of LV Bus Bars. (COMSA) • Disconnection of HV cables, if the cables are short, they will be replaced by new cables. (COMSA) • To be determined on the day of inspection, Week 39. • Disconnection of the control cables / Grounding cables. (COMSA) • HT chassis dismounting. (COMSA) • Dismantling of transformer from the support for transport (COMSA) Replacemnet of Transformers, LHC

  12. Transport • Existing Transfo: from the UJ76 to the surface of the LHC6. (EN-HE) • New Transformer: from LHC6 to UJ76 at same location. (EN-HE) • No problem of transport from UJ to arc and inside arc. Complete path until LHC6 surface to be confirmed by transport (EN-HE) Replacemnet of Transformers, LHC

  13. Transport (from UJ76 to arc) Replacemnet of Transformers, LHC

  14. Installation of new Transformer • Actions to be performed on the new transformer: • Extremities of HV cables (ARNOLD) • Connection of HV cables (ARNOLD) • Control circuit connection (COMSA) • Connection of the existing ground circuit (COMSA) • LV Bus bars connection (COMSA) • Transformer Envelope Reassembly (COMSA) • Installation of boundary barriers (COMSA) • HT cable test (EN-EL-EIC) • Transformer commissioning/Energization (EN-EL-EIC, EN-EL-OP)All the activities described will be carried out according to the operating mode of the contracting companies Replacemnet of Transformers, LHC

  15. Project Team Replacemnet of Transformers, LHC

  16. Co-activities • Co-activity with EL-FC if transport of transformer to be done from Pt. 8 • No co-activity foreseen in week 47for EMT305/76 Replacemnet of Transformers, LHC

  17. Risks • Electrical/Mechanical Risk • To ensure that workers are authorized for the electrical works they perform • Hot works: torch for retraction of sheaths for HV cables accessories • Fire extinguisher will be provided by contractor ARNOLD Replacemnet of Transformers, LHC