1 / 23

BLM 2008 Audit Follow Up

BLM 2008 Audit Follow Up. B. Dehning CERN BE/BI. System Overview. Beam energy. Beam energy. detector. CFC elec. Combiner. BIC. LBDS. Threshold comp. Tunnel: Detector: ionisation chamber + Secondary emission monitor Signal digitalisation and transmission by CFC card

Download Presentation

BLM 2008 Audit Follow Up

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BLM 2008 Audit Follow Up B. Dehning CERN BE/BI B.Dehning

  2. System Overview Beam energy Beam energy detector CFC elec. Combiner BIC LBDS Threshold comp. • Tunnel: • Detector: ionisation chamber + Secondary emission monitor • Signal digitalisation and transmission by CFC card • Surface VME cards: • Signal reception and threshold comparison • Combination of beam permit signals and surveys tasks • Database and Software: • Detailed system information in MTF • Detailed installation description in Layout • Reference settings for hardware are in LSA • Status of System: • after the 19 September event about 500 monitors have been dismounted re-installation is ongoing • Upgrade of frontend electronics was done (reset card and change in cable HV network) • Upgrades on data bases, check procedures and management software Tunnel Surface B.Dehning

  3. Auditors Report Content Recommendations by the Auditors 5.1 Determination and Management of Thresholds 5.1.1 Simulations of Loss Signals and Response Functions (6 items) (Barbara and Mariusz) 5.1.2 Management and Storage of Threshold Values (10 items) (Barbara and Mariusz. 16+17 Bernd) 5.2 Monitors & Electronics (Bernd) 5.2.1 Ionisation Chambers (2 items) (Bernd) 5.2.2 PCBs and Choice of Components (9 items) (Bernd) 5.2.3 FPGA Programming (5 items) (Bernd) 5.3 Environmental Aspects (5 items) (Bernd) 5.3.1 Electromagnetic Compatibility (EMC) (3 items) (Bernd) 5.4 Commissioning, Testing, and Documentation (6 items) (Bernd, last Barbara) B.Dehning

  4. Answers to the Audit Report (I) • 15+16. A “service level agreement” and or “Memorandum of understanding” has been discussed, but proposal has been rejected (it is not expected that it will be useful BE-CO). • 18. It is believed that a save beam permit inhibit is every time possible with the present tunnel cable network (enough charge in capacitors). Due to observation with one bunch losses, the decision was taken to separate IC from SEM and also ARC supply from SSS supply. And in addition in point 3 and 7 also the ICs of LSS had been grouped in high and medium losses. The effect is only visible in the chambers connected to the same HV box. • 19. SEM are calibrated in the beam lines H6 and H4 (see next transparency). • 20. Components and PCBs for 100 Spare cards are ordered and production is launched. We have 400 FPGA spares (CFC, tunnel card).      • 21. Not done for complete card. Will be done later. • 22. Mezzanine card for reset was developed and implemented on all the CFC-Cards, the reset can be provoked with a reset bottom, WorldFip (card wise, but not implemented yet) and the HV (point wise, operational).    • 23. Not done. Will be done later. B.Dehning

  5. Secondary Electrons per Protons on target • From histogram: • Mean ratio = 3.40 • Standard deviation = 0.92 • From Geant4 • Ratio = 3.95 • Stdev = 0.17 B.Dehning

  6. Answers to the Audit Report (I) • 15+16. A “service level agreement” and or “Memorandum of understanding” has been discussed, but proposal has been rejected (it is not expected that it will be useful BE-CO). • 18. It is believed that a save beam permit inhibit is every time possible with the present tunnel cable network (enough charge in capacitors). Due to observation with one bunch losses, the decision was taken to separate IC from SEM and also ARC supply from SSS supply. And in addition in point 3 and 7 also the ICs of LSS had been grouped in high and medium losses. The effect is only visible in the chambers connected to the same HV box. • 19. SEM are calibrated in the beam lines H6 and H4 (see next transparency). • 20. Components and PCBs for 100 Spare cards are ordered and production is launched. We have 400 FPGA spares (CFC, tunnel card).      • 21. Not done for complete card. Will be done later. • 22. Mezzanine card for reset was developed and implemented on all the CFC-Cards, the reset can be provoked with a reset bottom, WorldFip (card wise, but not implemented yet) and the HV (point wise, operational).    • 23. Not done. Will be done later. B.Dehning

  7. Answers to the Audit Report (II) • 24. Not done. Will be done later. • 25. + 26. PC; 3A max current of the regulator, nominal current are up to 350mA; 250mA; 800mA. Redundant PC will be installed when the test result support this decision. • 27. HV redundant PC exist . • 28. The filter is used for a pre integration, no signal is lost but stored in the capacitor and then discharged in the integrator. Test have been made with short pulses. Over voltage and over current has been tested 1500V@100us and 10A@100us. MTBF calculations have been done. We do not expect a increased failure rate, no action. • 29. FPGA synchronisation of asynchronous inputs. We are in a advanced state of defining and documenting FPGA design rules to be used for future projects in BI and CO. In addition, the mentioned example has been corrected. • 30. CFC card, remote control is added, which will reset the state machine if in a non defined state. • 31. We have invested in the construction of the vertical slice test system and a set of tests necessary to pass before releasing a new firmware (see next five transparencies). • 32. Unfortunately it is not still possible for this kind of review as the firmware for the BLETC and BLECS are needed to continue changing and adapting to the rest of the controls infrastructure. The complexity requires optimisations across the complete hierarchy. It will be done. B.Dehning

  8. BLM Acquisition Chain and CFC Simulator B.Dehning

  9. Vertical Slice test system Tests foreseen • Drive packets similar to those sent by the CFCs • Verify the response of the TC in case of correct input • Are the running sums produced correctly? • Are threshold comparisons done correctly? • Verify the response of the TC in case of erroneous input • CRC errors • Differences between the redundant optical channels Mezzanine PCB in production B.Dehning

  10. Test of Beam Permit Inhibit B.Dehning

  11. Beam Permit Inhibit Tests (I) • Compiled C code running on the Front End Computer (PowerPC architecture) • The threshold table of a given Threshold Comparator is repetitively modified to generate beam permit inhibit • The responses of the TC and the Combiner card are evaluated in every iteration • Complete run: test every possible combination of • 16 channels • 12 running sums • 32 energy levels = 6’144 iterations, about 18 hours running time • One test in each of the 8 IPs can be run in parallel B.Dehning

  12. Beam Permit Inhibit Tests (II) Tests runs • A total of 10 complete tests on 9 different cards in 5 crates: 61’440 accesses Error rates • Combiner (direct connection to the Beam Interlock): no errors • Threshold Comparator ≤ 1% of dump requests not logged • max. 62 out of the total of 6’144 • No errors writing the thresholds into the memory (iterative testing) Possible reasons for errors • Bugs in the logging part of the Threshold Comparator firmware • Bugs in LynxOS, the operating system of the FECs • Unhandled bus errors Tests run to investigate errors sources • A total of over 750’000 accesses have been done in 5 cards in 5 crates • Test code: TC and Combiner dump response read out and evaluated over numerous iterations in unchanged conditions • Error rates • Combiner (direct connection to the Beam Interlock): no errors • Threshold Comparator ≤ 0.01% of dump requests not logged max. a dozen out of 200’000 B.Dehning

  13. Answers to the Audit Report (II) • 24. Not done. Will be done later. • 25. + 26. PC; 3A max current of the regulator, nominal current are up to 350mA; 250mA; 800mA. Redundant PC will be installed when the test result support this decision. • 27. HV redundant PC exist . • 28. The filter is used for a pre integration, no signal is lost but stored in the capacitor and then discharged in the integrator. Test have been made with short pulses. Over voltage and over current has been tested 1500V@100us and 10A@100us. MTBF calculations have been done. We do not expect a increased failure rate, no action. • 29. FPGA synchronisation of asynchronous inputs. We are in a advanced state of defining and documenting FPGA design rules to be used for future projects in BI and CO. In addition, the mentioned example has been corrected. • 30. CFC card, remote control is added, which will reset the state machine if in a non defined state. • 31. We have invested in the construction of the vertical slice test system and a set of tests necessary to pass before releasing a new firmware (see next five transparencies). • 32. Unfortunately it is not still possible for this kind of review as the firmware for the BLETC and BLECS are needed to continue changing and adapting to the rest of the controls infrastructure. The complexity requires optimisations across the complete hierarchy. It will be done. B.Dehning

  14. Answers to the Audit Report (III) • 33. All sub-projects have been placed in a centralised BI-BL folder on SVN. In addition, common guidelines for the information to be included and the structure for its storage has been defined and followed for all sub-projects. Currently an effort is done to extend this also in the rest of the section and include the scripts for data analysis, threshold generation, GEANT4 simulations etc. • 34. The walkie-talkie not done yet, will be done later. • 35. Noise rejection of the CFC part often tested during operation. • 36. Magnetic fields no influence observed, CFC card has been tested up to 3000 Gauss. • 37 to 40. radiation issues of electronic discussed before, see next two transparencies. • 41. The tests with the source are essential, because it tests the whole chain at a very low currents 70 pA (10 times lower as any quench level). Batteries are only used in case of a non-functioning of the source tests (see next transparency). The likelihood of a failure after a disconnection is regarded as too high compared to a test at higher currents (every card has a LAB test record). • 42. Done last September (see next transparency). • 43. Not done yet, many channels are not re-installed yet will be done as soon as possible. • 44. Done, often tested, also foreseen in the test procedure before start-up. • 45. Vertical slice bench. On the way of its implementation. The installation was instead chosen to be in the LHC; this will provide the ability of direct comparison of the output signal of the vertical slice with the operational system. B.Dehning

  15. Radiation Tests and Error Rates • New radiation tests • CNGS mixed field • Prospero 1MeV neurons • PSI 60 MeV protons • Error rates due to tested radiation effects are negligible except for the ARC equipment. • ARC CFC digital part has redundant signal chain • ARC PC accelerated aging tests to be done B.Dehning

  16. 1 MeV Neutron Tests • In every (p and n) tests smooth change of output voltage observed. No SEE effect observed B.Dehning

  17. Answers to the Audit Report (III) • 33. All sub-projects have been placed in a centralised BI-BL folder on SVN. In addition, common guidelines for the information to be included and the structure for its storage has been defined and followed for all sub-projects. Currently an effort is done to extend this also in the rest of the section and include the scripts for data analysis, threshold generation, GEANT4 simulations etc. • 34. The walkie-talkie not done yet, will be done later. • 35. Noise rejection of the CFC part often tested during operation. • 36. Magnetic fields no influence observed, CFC card has been tested up to 3000 Gauss. • 37 to 40. radiation issues of electronic discussed before, see next two transparencies. • 41. The tests with the source are essential, because it tests the whole chain at a very low currents 70 pA (10 times lower as any quench level). Batteries are only used in case of a non-functioning of the source tests (see next transparency). The likelihood of a failure after a disconnection is regarded as too high compared to a test at higher currents (every card has a LAB test record). • 42. Done last September (see next transparency). • 43. Not done yet, many channels are not re-installed yet will be done as soon as possible. • 44. Done, often tested, also foreseen in the test procedure before start-up. • 45. Vertical slice bench. On the way of its implementation. The installation was instead chosen to be in the LHC; this will provide the ability of direct comparison of the output signal of the vertical slice with the operational system. B.Dehning

  18. Source Measurements • Left top: Signal, Offset and Difference vs monitor number (right of IP1) • Right top: offset signal distribution • Bottom left: source signal distribution: relative 0.064 spread B.Dehning

  19. Answers to the Audit Report (III) • 33. All sub-projects have been placed in a centralised BI-BL folder on SVN. In addition, common guidelines for the information to be included and the structure for its storage has been defined and followed for all sub-projects. Currently an effort is done to extend this also in the rest of the section and include the scripts for data analysis, threshold generation, GEANT4 simulations etc. • 34. The walkie-talkie not done yet, will be done later. • 35. Noise rejection of the CFC part often tested during operation. • 36. Magnetic fields no influence observed, CFC card has been tested up to 3000 Gauss. • 37 to 40. radiation issues of electronic discussed before, see next two transparencies. • 41. The tests with the source are essential, because it tests the whole chain at a very low currents 70 pA (10 times lower as any quench level). Batteries are only used in case of a non-functioning of the source tests (see next transparency). The likelihood of a failure after a disconnection is regarded as too high compared to a test at higher currents (every card has a LAB test record). • 42. Done last September (see next transparency). • 43. Not done yet, many channels are not re-installed yet will be done as soon as possible. • 44. Done, often tested, also foreseen in the test procedure before start-up. • 45. Vertical slice bench. On the way of its implementation. The installation was instead chosen to be in the LHC; this will provide the ability of direct comparison of the output signal of the vertical slice with the operational system. B.Dehning

  20. Noise Level Distributions • Procedure: • require data during nominal operation conditions of LHC • Choose most sensitive integration intervals • Set histogram max value to lowest quench threshold level (MB-magnet) • Overflows are interpreted as false signals B.Dehning

  21. Noise Signal Distribution of LHC 12. September 2008 • Checked: 15 hours in the nights between 12 to 16 September 2008 • Results:19 channels would have given false signals located on 4 electronics cards • Conclusion:It is assumed that this channels could have been repaired • 2009 checks are foreseen after reinstallation of BLM system Integration time 80 us Integration time 1.3 s B.Dehning

  22. Answers to the Audit Report (II) • 33. All sub-projects have been placed in a centralised BI-BL folder on SVN. In addition, common guidelines for the information to be included and the structure for its storage has been defined and followed for all sub-projects. Currently an effort is done to extend this also in the rest of the section and include the scripts for data analysis, threshold generation, GEANT4 simulations etc. • 34. The walkie-talkie not done yet, will be done later. • 35. Noise rejection of the CFC part often tested during operation. • 36. Magnetic fields no influence observed, CFC card has been tested up to 3000 Gauss. • 37 to 40. radiation issues of electronic discussed before, see next two transparencies. • 41. The tests with the source are essential, because in it test the hole chain at a very low current 70 pA, 10 times lower as any quench level). Batteries are only used in case of a non-functioning of the source tests (see next transparency). • 42. Done last September (see next transparency). • 43. Not done yet, many channels are not re-installed yet will be done as soon as possible. • 44. Done often tested, also foreseen in the test procedure before start-up. • 45. Vertical slice bench. On the way of its implementation. The installation was instead chosen to be in the LHC; this will provide the ability of direct comparison of the output signal of the vertical slice with the operational system. B.Dehning

  23. Conclusion • Several of the recommendations are implemented • Several will be followed up and decisions will be taken later (accelerated aging testing of PC and redundant implementations) • Documentation will be made available at:www.cern.ch/blm B.Dehning

More Related