An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mid Day Meal Scheme MDM-PAB Meeting –Sikkim on 12.03.2013 Ministry of HRD Government of India

  2. Review of Implementation of MDMS in SIKKIM(Primary + Upper Primary)(1.4.2012 to 31.12.2012) Part-I Ministry of HRD, Govt. of India

  3. Coverage of Institutions (Primary) No. of Institutions MIS data also indicates the same number of institutes. Ministry of HRD, Govt. of India

  4. Coverage of Institutions (Upper Primary) No. of Institutions MIS data also indicates the same number of institutes Ministry of HRD, Govt. of India

  5. Coverage of Children (Primary ) No. of Children (in Thousands) 92% 92% 91% Percentage indicates coverage of children against the Total Enrollment Ministry of HRD, Govt. of India

  6. Coverage of Children (Upper Primary) No. of Children (in Thousands) 89% 96% 90% Percentage indicated coverage against Enrollment Ministry of HRD, Govt. of India

  7. District wise : Less Coverage Primary Children Upper Primary Children

  8. District Level Health Survey

  9. No. of Working Days MDM Served – Primary No. of Working Days Total Working Days approval for 2012-13: 220 Days Ministry of HRD, Govt. of India

  10. No. of Working Days MDM Served : ( Upper Primary ) No. of Working Days Total Working Days approval for 2012-13: 220 Days Ministry of HRD, Govt. of India

  11. Approval Vs Achievement: No of Meals (P + UP) upto 3rd Qtr No. of Meals (in crore) 91% 102% 86% Ministry of HRD, Govt. of India

  12. Utilization of Food Grains(01.04.12 to 31.12.12) Foodgrains (in MTs) 79% % utilization is against allocation Ministry of HRD, Govt. of India

  13. FOOD GRAINS : ALLOCATION vs UTILISATION Quantity in MTs 77% 79% 79% Ministry of HRD, Govt. of India

  14. Payment of Cost of Food grains to FCI Cost of Food Grain (Rs. In Lakhs ) 100% Ministry of HRD, Govt. of India

  15. COOKING COST: ALLOCATION VS UTILISATION Rs in Crores 95% 84% 54% Ministry of HRD, Govt. of India

  16. Engagement of Cooks-cum-Helpers No of CCH Ministry of HRD, Govt. of India

  17. Honorarium to Cooks-cum-Helpers Rs. In Crore 94% Ministry of HRD, Govt. of India

  18. MME : ALLOCATION vs UTILISATION Rs in Lakhs 21% 21% 7% Ministry of HRD, Govt. of India

  19. Transportation Assistance : Allocation vs Utilisation Rs in Lakhs 79% Ministry of HRD, Govt. of India

  20. Construction of Kitchen cum Stores Total Units sanctioned : 859 Progress (in %) MIS data shows that kitchen-cum-store completed in 775 schools. Ministry of HRD, Govt. of India

  21. Procurement of Kitchen Devices under MDM Total Sanctioned : 879 Kitchen Devices Progress (in %) MIS data shows availability of kitchen devices in 800 schools. Ministry of HRD, Govt. of India

  22. Coverage : School Health Programme and Inspections No. of Institutions 96% 50% Ministry of HRD, Govt. of India

  23. Coverage :School Health Programme No information submitted on the spectacles distributed to the children. Ministry of HRD, Govt. of India

  24. Availability of Infrastructure as per MDM MIS Data State has not indicated availability of infrastructure in its QPR/AWP&B 2013-14 except for 447 LPG connections. Ministry of HRD, Govt. of India

  25. SCORE CARD- ALL COMPONENTS Ministry of HRD, Govt. of India

  26. ISSUES SSMC Meetings were not held during 2011-12 and 2012-13. Delay of 4-5 months in the release of funds to schools Schools reimbursed central assistance against expenditure. State assured during last PAB to review this system. But no change made so far. Central assistance solicited for Kitchen-cum-stores which were badly damaged by earth quake/floods. PAB advised State during 2012-13 to seek assistance from SSA. 5. Low utilization of MME (only 21 % by end of 3rd Quarter 2012-13).

  27. Findings of North Bengal University-MI • Hot cooked MDM served daily in the school premises. • MDM not served on examination days in 2 schools (Meyong Primary School and Voong P.S). • Tinchin Junior High School reported that quantity is not enough for class 7 and class 8 students. • Problem in delivery of food grains to Naga JHS, Nampatam PS and Voong PS due to damaged road on account of earthquake and flash floods. • Schools received Cooking Cost in October 2012. • Rice given daily but Pulses are not given. • SMC members are not aware of their responsibilities and not conversant with maintaining cooking cost accounts. • Water connection is outside the kitchen. • 90% of Cooks belong to SC.

  28. Analysis of State’s Proposal for 2013-14 Part -2 Ministry of HRD, Govt. of India

  29. Proposal for 2013-14 : Children (Primary) No. of children (in thousands) PAB Approval 12-13 Availed MDM in Q-1 Availed MDM in Q-2 Availed MDM (9 months) Proposal for 2013-14 Enrolment Availed MDM in Q-3 Ministry of HRD, Govt. of India

  30. Proposal for 2013-14 : Children (Upper Primary) No. of children (in thousands) PAB Approval for 12-13 Availed MDM (9 months) Proposal for 2013-14 Enrolment Availed MDM in Q-2 Availed MDN in Q-1 Availed MDM in Q-3 Ministry of HRD, Govt. of India

  31. Proposal for Cook-cum-helpers for 2013-14 * Secretary (HRDD)Sikkim has informed in response to the deficiency letter that inter-district adjustments will be made to avoid additional requirement. Ministry of HRD, Govt. of India

  32. Proposal for Construction of Kitchen-cum-Store The State has also submitted proposal for the construction of 72 kitchen-cum-stores which were damaged by earth quake in 2011. This proposal is already under process separately. Ministry of HRD, Govt. of India

  33. Proposal for Procurement of Kitchen Devices • Kitchen Devices Sanctioned during 2007-08 • 443 Kitchen Devices Sanctioned during 2012-13 for replacement Ministry of HRD, Govt. of India

  34. Proposals and Recommendations Ministry of HRD, Govt. of India

  35. The MDM Logo should be Widely Publicized. It may be Painted at prominent Places on the outside wall of the school. Ministry of HRD, Govt. of India